Nevada Approves 510-Megawatt Gas Plant for Switch
Regulators cleared a natural gas plant on a former refinery site in northern Nevada to power Switch's data center operations.
Updated on Nov. 10, 2026 in Data Centers

Live Poll
Do you think new gas plants for data centers are worth it for your area?
The Nevada Public Utilities Commission approved a 510-megawatt natural gas power plant on a roughly 20-acre site at the former Sierra Biofuels Refinery in the Tahoe-Reno Industrial Center. Switch has disclosed it is the plant's intended off-taker and ultimate owner.
Why it matters
The plant is a behind-the-meter facility that bypasses the utility grid queue, reflecting that NV Energy does not currently have infrastructure to immediately serve large data center demand in the region. It signals how data center growth is reshaping Nevada's energy planning.
The plant will use nine gas turbines and draw 10,000 to 20,000 gallons of water per day during construction, with 145 acre feet per year over its life cycle. Whether projected data center demand will drive capacity needs above 20 gigawatts by 2050 has not been established.
The players
Switch
Switch is a data center company that is the intended off-taker and ultimate owner of the approved natural gas plant.
Nevada Public Utilities Commission
The Nevada Public Utilities Commission is the state regulatory body that reviewed and approved the power plant applications.
NV Energy
NV Energy is the utility serving Nevada whose systemwide generating capacity and grid infrastructure are central to the plant's behind-the-meter rationale.
The details
Nexus Fulcrum LLC filed the application in June, initially identifying only an unnamed single off-taker. Switch later disclosed in October that it is the intended off-taker and ultimate owner, and the commission approved the plant at its Tuesday regular agenda meeting. Separately, the commission approved two temporary gas plant requests from Fleet Data Centers totaling 362 megawatts in September.
Timeline
June: Nexus Fulcrum LLC filed the application with the commission.
September: The commission approved two Fleet Data Centers gas plant requests.
October: Switch disclosed it is the intended off-taker and owner.
Tuesday: The commission approved Switch's 510-megawatt plant at its regular agenda meeting.
First quarter 2027: Construction is scheduled to begin, finishing in 2029.
Seasonal Patterns
The approval follows a projection that data centers will rise from 5 percent of NV Energy electricity sales today to 64 percent by 2046. The plant is an early concrete response to that trajectory in northern Nevada.
Nevada residents may see changes in electricity planning as data center demand grows, since data centers are projected to rise sharply as a share of NV Energy electricity sales. The plant itself bypasses the utility grid queue, so its direct effect on household power bills is not addressed in the approval record.
The takeaway
Large data center loads are pushing utilities and regulators to approve new generation outside traditional grid queues. Readers tracking Nevada power costs should watch how these projects affect long-term capacity planning.
What happens next
Construction of the plant is scheduled to begin in the first quarter of 2027 and finish in 2029.
Further reading
Explore more on data centers and how they are reshaping regional power planning.
Source note: This article includes information reported by Las Vegas Review-Journal.