Spartan Metals Eyes $683 Million Tungsten Mine
A preliminary study outlines an underground tungsten and molybdenum mine at Victorio, New Mexico, with a 24-year operating life.
Updated on Nov. 19, 2026 in Industry

Spartan Metals released a preliminary economic assessment estimating $683 million to build an underground tungsten and molybdenum mine at Victorio, New Mexico. The project sits about 440 km southwest of Santa Fe.
Why it matters
The United States last mined tungsten commercially in 2015, and China accounts for about 85% of global capacity to refine ammonium paratungstate. A domestic source of the metal would reduce reliance on that concentration of supply.
The preliminary economic assessment projects an after-tax net present value of $2.14 billion at an 8% discount rate and a 31% internal rate of return, against $2.03 billion in sustaining spending over the mine's life. At the lowest tested prices, the NPV drops to $392 million, and the study does not resolve whether prices would hold at those levels.
The players
Spartan Metals
Spartan Metals is a Toronto-listed mining company advancing the Victorio project in New Mexico.
Donegan Resources
Donegan Resources is the company that granted Spartan an option on the core claims at Victorio.
The details
Victorio would use block caving, an underground method that uses gravity to break the rock. The study projects annual recovery of about 4,100 tonnes of tungsten trioxide contained in ammonium paratungstate and 8.65 million lb. of molybdenum in concentrate.
Timeline
March 2026: Spartan and Donegan Resources signed an option agreement on core claims.
August 2026: Resource estimate updated for Victorio deposits.
November 19, 2026: Preliminary economic assessment released.
2034: Feasibility study deadline under the option agreement.
Market Landscape
The Victorio project would add a domestic mining source to a tungsten supply chain in which China holds about 85% of ammonium paratungstate refining capacity. Because the United States last mined tungsten commercially in 2015, a New Mexico mine would put a U.S.-based source into a market that currently has few alternatives.
For New Mexico residents and businesses, the project would bring a large underground mine and its associated jobs and infrastructure, though it remains years from construction. Consumers are unlikely to see any change in tungsten-dependent products until a mine is built and in operation.
The takeaway
Domestic tungsten supply depends on whether a preliminary economic case becomes a financed, permitted mine, a step that remains years away for Victorio. Tracking the prefeasibility work and the 2034 feasibility deadline will show whether New Mexico gains a real alternative source.
What happens next
Spartan plans to advance Victorio to prefeasibility, and the study recommends $13.2 million of drilling, metallurgical testing and water and tailings studies before that stage.