Longview Wins New Mexico Transmission Line Contract
Southwest Power Pool selected Longview Infrastructure to build a 50-mile, 115-kV line serving oil and gas electrification in Lea and Eddy counties.
Updated on Nov. 19, 2026 in Utilities

Live Poll
Do you expect your electricity bills to rise in the next few years?
Southwest Power Pool selected Longview Infrastructure to develop a roughly 50-mile, 115-kV transmission line connecting the Phantom, Battle Axe, Ponderosa and Dollarhide substations across Lea and Eddy counties in New Mexico. The selection was made November 17, 2026, after a five-member independent industry expert panel unanimously recommended Longview's proposal over two other competing bids.
Why it matters
Oil and gas operators in southeastern New Mexico are shifting equipment from diesel-powered operations to electric alternatives, creating new firm load on the regional grid. SPP's 2025 Integrated Transmission Plan identified approximately 4,000 MW of new firm load driven largely by that electrification.
The line spans about 50 miles at 115 kV, against a forecast of roughly 4,000 MW of new firm load in the region, a projection drawn from SPP's 2025 transmission plan. Longview has targeted June 2029 for the line to enter service, and the source does not address project cost.
The players
Southwest Power Pool
A regional transmission organization that coordinates grid reliability and transmission planning across several central U.S. states, including New Mexico.
Longview Infrastructure
A developer of energy transmission infrastructure, backed by the investment firm Stonepeak, that won the right to build and own this New Mexico line.
Stonepeak
An infrastructure investment firm that backs Longview Infrastructure's transmission development work.
The details
The project was selected through SPP's competitive Transmission Owner Selection Process, with Longview Infrastructure Southwest, LLC designated as the transmission owner. The line connects the Phantom, Battle Axe, Ponderosa and Dollarhide substations, and Longview is backed by Stonepeak.
Timeline
November 17, 2026: Southwest Power Pool selects Longview Infrastructure for the transmission project.
June 2029: Longview's target in-service date for the transmission line.
Market Landscape
The award translates the 4,000 MW load forecast in SPP's 2025 Integrated Transmission Plan into a concrete transmission build, tying the grid planning process to oil and gas electrification in the Permian region of southeastern New Mexico. It also shows developers such as Longview competing for transmission ownership as electrification drives new demand.
For New Mexico residents and businesses, the line is aimed at adding capacity for new electric loads in Lea and Eddy counties, which the source ties to oil and gas electrification. The source does not describe any direct change to residential electricity rates or service.
The takeaway
Electrifying oil and gas operations is pulling grid investment into southeastern New Mexico, and transmission projects like this one are the physical step that makes that load possible. Watching whether the June 2029 schedule holds will show how quickly the region's new demand can be served.
Further reading
For broader context on grid expansion, see Utilities coverage across New Mexico.
Source note: This article includes information reported by Constructionreview.