Crews Advance 42nd Street and DeMers Underpass
Crews made significant progress on the 42nd Street and DeMers Avenue underpass project during the 2026 construction season.
Updated on Nov. 19, 2026 in Business

Live Poll
Do you think long road construction projects are worth the disruption in your community?
Crews built a temporary DeMers Avenue bypass and shared-use path, installed a new water main under BNSF Railway tracks, built a temporary rail line, and finished excavation for both bridges. The DeMers Avenue and 42nd Street intersection is closed, and traffic is routed onto the bypass that connects to South 42nd Street.
Why it matters
The closure and detours affect commuters moving through the Grand Forks area, and the work zone is posted at 20 mph. Drivers and pedestrians in the area will face these changes until the new bridges open.
The posted work zone speed limit is 20 mph across the construction area. Excavation for both bridges is complete, while bridge foundation and support work will continue over winter as weather allows.
The players
Grand Forks, N.D.
Grand Forks is a city in eastern North Dakota that serves as the regional hub for the Red River Valley, home to the University of North Dakota.
The details
Crews built the temporary DeMers Avenue bypass and shared-use path, which provides east-west pedestrian access and is cleared of snow in winter. Passenger vehicles are detoured via Gateway Drive/U.S. Highway 2, 17th Avenue South and Columbia Road, while 42nd Street is closed north of the bypass up to James Ray Drive.
Timeline
2026: Bypass, water main, temporary rail line and bridge excavation completed.
Winter 2026-27: Bridge foundation and support work continues as weather allows.
Spring 2027: Full construction resumes.
Summer 2027: DeMers Avenue traffic is scheduled to shift onto the new bridges.
Fall 2027: 42nd Street is scheduled to reopen.
Construction Corridor
The project separates DeMers Avenue and 42nd Street traffic from the BNSF Railway tracks, continuing the grade-separation approach used along the corridor. Relocating the water main and building a temporary rail line allow the crossing to be rebuilt without interrupting rail service.
Drivers should use the posted detours via Gateway Drive/U.S. Highway 2, 17th Avenue South and Columbia Road and observe the 20 mph work zone limit. Pedestrians can use the shared-use path along the DeMers Avenue bypass, which is cleared of snow in winter.
The takeaway
Planning around the closure now will reduce delays through 2027, when traffic moves onto the new bridges and 42nd Street reopens.
What happens next
Full construction resumes in spring 2027, DeMers Avenue traffic shifts onto the new bridges in summer 2027, and 42nd Street is scheduled to reopen in fall 2027.
Further reading
For related local projects, see Construction coverage across Grand Forks.
Source note: This article includes information reported by The Bismarck Tribune.