Forum Markets Proposes High Point AI Data Center
Palm Beach-based Forum Markets Inc. has proposed an AI data center campus at 200 Mandustry St. in south High Point.
Updated on Nov. 25, 2026 in Data Centers

Live Poll
Would you support a large AI data center being built in your community?
Forum Markets Inc., a Palm Beach, Florida company, has proposed an AI data center campus on a five-acre industrial lot at 200 Mandustry St. in south High Point. The company also received a stop-work order on its separate South Road property.
Why it matters
The project shows developers targeting existing powered sites to speed data center construction in North Carolina, where the pipeline of planned facilities far exceeds the number now operating. For High Point residents, the proposal raises questions about how new large-scale power demand will be managed locally.
The Mandustry Street site holds six buildings totaling about 11,000 square feet with 9 megawatts of live utility power, and 6 megawatts are expected to be energized in the first quarter of 2027. Whether that timeline holds has not been confirmed.
The players
Forum Markets Inc.
A Palm Beach, Florida company pursuing the High Point AI data center campus through a joint venture with Edge Mode Inc.
Edge Mode Inc.
A Texas-based company partnering with Forum Markets on a joint venture focused on existing powered data center sites.
Energy Storage Solutions
A company that withdrew a proposed $19.2 billion AI data center project in Edgecombe County in July 2026.
The details
Forum Markets chose the site because it already has power and permits for data center use, and the project is tied to a joint venture with Texas-based Edge Mode Inc. that targets existing powered sites. The company acquired the property in September 2026.
Timeline
September 2026: Forum Markets acquired the 200 Mandustry St. site.
July 2026: Energy Storage Solutions withdrew a $19.2 billion Edgecombe County AI data center project.
First quarter of 2027: First 6 megawatts expected to be energized at the High Point site.
Seasonal Patterns
The High Point proposal adds to a North Carolina pipeline of at least 54 planned data center buildings totaling 4,258 megawatts, compared with just 13 operating buildings statewide as of September 2026. Developers are increasingly targeting sites that already hold power and permits as the state's growth accelerates.
For High Point residents, the project could bring new large-scale power demand to a site that already has utility service and permits. The timeline for the first 6 megawatts to come online in the first quarter of 2027 depends on transformer deliveries that may slip.
The takeaway
Data center projects are moving toward existing powered sites, which can speed construction but also concentrates new electricity demand in specific communities. Residents who want to track local impacts should follow permit and rezoning actions.
Further reading
For broader context, explore more coverage in our Data Centers section.
Source note: This article includes information reported by Hoodline.