High Point Weighs $70M Koonce City Lake Dam Replacement

Congress authorized a future $20 million appropriation as state regulators found the existing Arnold J. Koonce City Lake dam falls short of current safety standards.

Updated on Nov. 25, 2026 in City Hall

High Point Weighs $70M Koonce City Lake Dam Replacement

Live Poll

Do you trust your local government to manage aging public infrastructure well?

Congress authorized a future $20 million appropriation toward a replacement for the Arnold J. Koonce City Lake dam in High Point, though the authorization does not cover the full cost. State regulators determined the existing dam does not meet current safety requirements for stability or spillway capacity, though the city says it is not currently failing and is considered structurally sound.

Why it matters

Replacement construction is estimated at more than $70 million, leaving a large funding gap for the city to address. The city decided that building a new dam farther downstream was more cost-effective than retrofitting the aging structure, which has held up for roughly 100 years.

The Water Resources Development Act of 2026 authorized a future $20 million appropriation, which does not cover the full project cost, while estimates for replacement construction range from $32.5 million to more than $70 million. Funding sources for the balance have not been identified in the available reporting.

The players

Robby Stone

Robby Stone is a public official whose role in High Point civic affairs is referenced in the city's reporting on the dam project.

The details

The city decided to build a new dam farther downstream near the West Main Street bridge rather than retrofit the existing structure, and the current dam will be demolished once the replacement is in place. High Point Public Services began serious discussions about the dam's future in August 2022, and the city hired Schnabel Engineering South, based in Greensboro, to design the new dam.

Timeline

  1. May 2017: Schnabel began evaluating whether to rehabilitate or replace the dam.

  2. August 2022: High Point Public Services began serious discussions about the dam's future.

  3. 2023: The city purchased two Knollwood Drive properties for project access and construction staging.

  4. 2028: Earliest projected construction start, if approved.

Civic Context

The federal authorization under the Water Resources Development Act of 2026 provides only part of the funding needed, so High Point must cover the gap through its own resources or additional appropriations. The project's timeline, with at least 25 months of design and 12 months of permitting, means construction would not begin before 2028, if then.

Residents downstream, including those at Jamestown Village Apartments, depend on the dam's safety, and the city's decision affects the timeline and cost of that protection. Property owners near Knollwood Drive are affected by the city's purchase of two properties for construction staging.

The takeaway

High Point's dam replacement illustrates how federal authorizations often cover only part of major infrastructure costs, leaving cities to plan for the balance. Residents should watch for updated cost estimates and funding decisions as design and permitting proceed.

What happens next

The project faces at least 25 months of design work and 12 months of permitting before construction can begin, with construction not expected before 2028 if approved.

Further reading

Follow local decisions on the project in the City Hall section for High Point.

Source note: This article includes information reported by Hoodline.