Opposition Fills Hearing on 765-kV Minnesota Power Line

All 24 speakers at a Sherburn hearing opposed the PowerOn Midwest transmission project, which still needs a state Certificate of Need.

Updated on Nov. 13, 2026 in Utilities

Abstract editorial illustration of steel lattice transmission towers receding across flat Minnesota farmland under a pale sky, evoking the proposed power line.
Twenty-four speakers opposed PowerOn Midwest's 765-kilovolt transmission line at a Minnesota Public Utilities Commission hearing in Sherburn, as the project still awaits a state Certificate of Need. AI Illustration. Upload story photo >

Live Poll

Should Minnesota approve the new 765-kilovolt power line through southern counties?

Twenty-four people spoke against the PowerOn Midwest transmission line at a Minnesota Public Utilities Commission hearing in Sherburn. The proposed 765-kilovolt line would run from South Dakota across southern Minnesota, through Martin County, to Dakota County.

Why it matters

The project must receive a state Certificate of Need before moving forward, and Great River Energy says the line is required to maintain electric reliability as demand grows. Opponents, including Martin County Commissioner Richard Koons, argue that local counties are losing population and that a smaller project could meet near-term needs.

The 765-kilovolt line would carry power from South Dakota across southern Minnesota, and Great River Energy projects about 25 percent growth in power consumption over 20 years. Retired Xcel Energy employee Kent Scholl argued a smaller project could meet near-term reliability needs.

The players

Minnesota Public Utilities Commission

The state regulatory body that reviews energy infrastructure projects and will decide whether the PowerOn Midwest line receives a Certificate of Need.

Great River Energy

A Minnesota electric cooperative and the utility representatives say the transmission line is needed to maintain reliability.

Richard Koons

A Martin County commissioner who told the hearing that local counties are losing population.

Kent Scholl

A retired Xcel Energy employee who argued a smaller transmission project could meet near-term reliability needs.

The details

Public Utilities Commission Administrative Law Judge Joseph Meyer will issue a report with recommendations by February 15, 2027. The Commission is expected to decide on the Certificate of Need around March or April 2027, and public comments may be submitted by email, mail, fax or an online form before the 4:30 p.m. deadline on December 7, 2026.

Timeline

  1. Thursday: Public Utilities Commission hearing in Sherburn, with all 24 speakers opposing the project.

  2. December 7, 2026, 4:30 p.m.: Public comment period closes.

  3. February 15, 2027: Administrative Law Judge report with recommendations due.

  4. March or April 2027: Expected Commission decision on the Certificate of Need.

Regulatory Path

The proposal must clear Minnesota's Certificate of Need review for large energy facilities, and the opposition's call for a smaller alternative sets up a direct test of whether the 765-kilovolt scale is justified. The Commission's decision in spring 2027 will show whether that review accepts the utility's reliability case.

Residents along the proposed route in Martin and Dakota counties could see the line built near their land and their electric bills shaped by its cost. Anyone who wants the Commission to weigh their views can submit comments by email, mail, fax or the online form before the December 7 deadline.

The takeaway

Public comment can still shape the Commission's review of the PowerOn Midwest line before the December deadline. Anyone with a stake in the route or the cost should weigh in through the official channels.

What happens next

Public comments are due by 4:30 p.m. on December 7, 2026, and the Administrative Law Judge's report is due February 15, 2027, ahead of a Commission decision expected in March or April 2027.

Further reading

For background on how these projects are reviewed, see Utilities coverage across Minnesota.

More information

Submit your views through the Minnesota PUC public comment form and instructions before the December 7, 2026 deadline.

Source note: This article includes information reported by 1370 AM.