Woodbury Approves Valley Creek Road Overhaul
The City Council voted 5-0 to advance a roughly $10.57 million improvement project on a 1.5-mile corridor.
Updated on Nov. 19, 2026 in City Hall

Live Poll
Do you support your city paying more for road and trail upgrades this way?
Woodbury City Council voted 5-0 on November 18, 2026, to approve improvements to about 1.5 miles of Valley Creek Road between Interstate 494 and Bielenberg Drive. The preliminary project estimate is $10.57 million, with Woodbury's estimated share at $2,037,660.
Why it matters
The corridor carries roughly 12,000 to more than 33,000 vehicles daily, and the signals at several intersections have reached the end of their service life. The city's preliminary share is $167,660 above the $1.87 million funding plan it previously adopted, so the remaining financing will need to be closed out.
The preliminary estimate puts the project at $10.57 million, with Woodbury's share at $2,037,660, which is $167,660 above the $1.87 million the city previously adopted. Final figures depend on bids not yet opened and a cost-sharing agreement not yet signed.
The players
Woodbury City Council
The elected governing body of Woodbury, Minnesota, which approves municipal budgets, infrastructure plans and funding agreements for the city.
Washington County
The county government that is leading the Valley Creek Road project and will share in its financing with the city of Woodbury.
The details
The western stretch from Interstate 494 through Woodlane Drive is slated for resurfacing, while the section east of Woodlane Drive would receive more extensive pavement replacement through Bielenberg Drive. Pedestrian ramps that fail current accessibility standards would also be replaced, and the aging traffic signals at Valley Creek Plaza, Queens Drive and Bielenberg would be upgraded.
Timeline
November 18, 2026: City Council voted 5-0 to approve the improvements.
February 2027: City and county consider detailed plans and a bid date.
April 2027: Bid opening.
May or June 2027: Cost-sharing agreement and assessment hearing.
July through October 2027: Construction, with substantial completion expected in October.
Need to Know
The project relies on the city's municipal state-aid revenue, the same funding channel Woodbury uses for eligible arterial roads under Minnesota's state-aid system. Its financing plan combines that revenue with stormwater and water-and-sewer funds, and the city's preliminary share now exceeds its previously adopted $1.87 million plan.
Drivers on Valley Creek Road can expect construction from July through October 2027, with substantial completion expected that October. Commercial property owners along the corridor are included in the preliminary assessment, which identifies 19 commercial parcels for potential cost-sharing.
The takeaway
Local road projects are often financed through a mix of state aid, county partnerships and utility funds, so preliminary cost estimates can shift once bids are received. Residents tracking the Valley Creek Road work should watch for the bid opening and the cost-sharing agreement, which will determine the final price.
What happens next
The city and county will consider detailed plans and a bid date in February 2027, with bids opening in April 2027 and a cost-sharing agreement and assessment hearing to follow in May or June 2027.
Further reading
For more on how local decisions like this one get made, browse the City Hall coverage on Wisevoter.
Source note: This article includes information reported by Woodbury News Net.