Lighthouse Sustainability withdrew its interest in a data center proposal of more than $10 billion on 423 acres in Delhi Township, near Lansing. Economic development officials announced the withdrawal on Monday, Nov. 9.

Why it matters

The withdrawal follows a yearlong township moratorium on data centers and a resolution calling on developers to drop the project, citing an overwhelming amount of negative public input. The outcome reflects growing local opposition to large data center projects across Michigan, where at least eight other projects have been canceled or denied.

The proposal was valued at more than $10 billion on 423 acres, and Lighthouse had pledged a $20 million community-managed fund and projected more than $50 million in new annual taxes. A $6.5 million state grant for site development and the fate of the at least eight other Michigan projects that were canceled or denied remain unclear in the record.

The players

Lighthouse Sustainability

A developer selected by LEAP to shape the proposed data center, which withdrew its interest after local opposition.

Delhi Township

A township in Ingham County near Lansing that passed a moratorium and opposition resolution against the data center project.

LEAP

A regional economic development group that selected Lighthouse Sustainability to pursue the Delhi Township data center plan.

The details

Delhi Township officials passed a resolution on Friday, Oct. 30, calling on developers to drop the project at a hastily arranged meeting, after the township withdrew from the LEAP economic development group on Oct. 28. LEAP had selected Lighthouse to pursue the plan on property owned by DTN Development.

Timeline

  1. April: Delhi Township passed a yearlong data center moratorium.

  2. Oct. 27: The data center proposal was announced to the media.

  3. Oct. 28: Delhi Township withdrew its membership from LEAP.

  4. Friday, Oct. 30: Township passed a resolution calling for the project to be dropped.

  5. Monday, Nov. 9: Economic development officials announced Lighthouse's withdrawal.

Roadmap

Lighthouse's withdrawal extends a pattern in which at least eight other Michigan data center projects have been canceled or denied. The Delhi Township case shows how local moratoriums and opposition resolutions are becoming a recurring obstacle for large data center proposals in the state.

Residents in Delhi Township and nearby communities will not see the proposed $10 billion facility or the projected $50 million in new annual taxes for local schools and roads. The withdrawal means the community-managed $20 million fund pledged by Lighthouse will not be created for this project.

The takeaway

Local opposition has become a decisive factor for large data center proposals in Michigan. Residents following land-use decisions should watch township meetings and moratorium votes closely, since these actions can end projects before they start.

Further reading

Explore more on Data Centers to see how similar projects are shaping communities across Michigan.

Source note: This article includes information reported by Mlive.

Live Poll

Should your community be able to block a large data center near homes?