Regulators Send NECEC Forest Plan Back for Revision

Maine's Board of Environmental Protection voted 5-1 to return the conservation plan tied to the New England Clean Energy Connect line to staff.

Updated on Nov. 19, 2026 in Utilities

Bold flat-color editorial illustration of stacked cut logs at a forest edge with a straight cleared power corridor receding into the distance.
Maine regulators voted 5-1 to send the forest conservation plan for the NECEC transmission line back to staff, the second delay in two months covering 50,000 acres. AI Illustration. Upload story photo >

Live Poll

Do you trust big companies to keep their environmental promises?

Maine's Board of Environmental Protection voted 5-1 to send the forest conservation plan for the New England Clean Energy Connect power line back to Department of Environmental Protection staff for further revisions. It is the second time in two months that regulators have delayed a final decision on the plan.

Why it matters

The plan governs logging and conservation across 50,000 acres connected to a $950 million transmission line now carrying Canadian hydropower to Massachusetts. The appeal, brought by conservation groups, centers on whether harvest schedules leave set-aside forest vulnerable to clearcutting.

The 5-1 board vote sent the order back to staff, which would have required NECEC Transmission LLC to accept logging bans across 10,000 acres of western Maine forest. The revised conditions the board wants have not been detailed, and the appellants' attorney said they could not be met within the expected 60 days.

The players

NECEC Transmission LLC

The company that built and operates the New England Clean Energy Connect transmission line, which carries Canadian hydropower into Massachusetts.

Weyerhaeuser

A large American timberland and forest products company whose logging schedule on set-aside land is at the center of the appeal.

Appalachian Mountain Club

A nonprofit conservation and outdoor recreation organization founded in 1876 that co-filed the appeal of the forest plan.

The details

The appeal was filed by the Appalachian Mountain Club, Natural Resources Council of Maine, Maine Audubon and Trout Unlimited, who claimed the approved plan let Weyerhaeuser clearcut set-aside land under a shifting logging schedule. The board backed strengthening the original plan so mature stands remain uncut once they reach maturity, while the state order would have measured forest health by trunk width and total wood rather than height.

Timeline

  1. January 2026: The transmission line went online carrying Canadian hydropower.

  2. 2026: The original forest management plan was approved.

  3. September 2026: DEP recommended the board reject the appeal.

  4. November 19, 2026: The board voted 5-1 to send the plan back to staff.

Market Landscape

The dispute over the NECEC forest order shows how large transmission builds in Maine are now tied to conservation conditions negotiated with timberland owners. Regulators are testing whether those conditions can be enforced against a major forest landowner like Weyerhaeuser.

Maine households and businesses could see the cost and reliability of the transmission line's hydropower affected by how long the forest plan takes to finalize. Logging and access rules on the 10,000-acre sanctuary also shape recreation and land use for residents in western Maine.

The takeaway

Conservation conditions attached to energy infrastructure can take months to resolve, so ratepayers and landowners alike should track how the revised order is written. The outcome will show whether set-aside protections are enforceable in practice.

Further reading

Explore more Maine utilities coverage for context on the state's energy infrastructure projects.

Source note: This article includes information reported by Portland Press Herald.