Maine Board Sends Forest Plan for NECEC Back

Regulators delayed a final decision on a 50,000-acre conservation plan for the New England Clean Energy Connect power line for a second time.

Updated on Nov. 19, 2026 in Utilities

Wide view of a straight cleared corridor cutting through dense mature spruce and fir forest under overcast northern sky, with a wall of intact old-growth canopy beyond.
Maine regulators sent a 50,000-acre forest conservation plan for the New England Clean Energy Connect power line back to staff for revisions after environmental groups challenged logging rules on set-aside land. AI Illustration. Upload story photo >

Live Poll

Should companies building major infrastructure be required to protect nearby forests?

The Maine Board of Environmental Protection voted 5-1 to return the forest conservation plan for the New England Clean Energy Connect transmission line to Department of Environmental Protection staff for further revisions. The board, meeting in Augusta, said it supports strengthening the original forest management plan so mature tree stands remain standing longer.

Why it matters

The decision leaves the 50,000-acre conservation plan unresolved and keeps a dispute over logging rules in western Maine's forests open. The vote reflects an appeal by environmental groups who argue the original plan allowed clearcutting on set-aside land.

The board voted 5-1 to send the plan back, and the proposed order would have required NECEC Transmission LLC to set aside a 10,000-acre no-cut sanctuary and ban harvesting of stands 100 years old or older. The revised conditions cannot be met within the expected 60 days, and no final timeline has been set.

The players

NECEC Transmission LLC

The developer behind the New England Clean Energy Connect transmission line, which carries Canadian hydropower to Massachusetts.

Weyerhaeuser

A major timberland owner whose logging schedule on set-aside land was challenged in the appeal of the forest plan.

Avangrid

The energy company that is part of the corporate group associated with the New England Clean Energy Connect project.

The details

The board rejected other state recommendations and directed staff to rework the plan. The appeal of the original 2026 forest management plan was filed by the Appalachian Mountain Club, Natural Resources Council of Maine, Maine Audubon and Trout Unlimited, who claimed the plan let Weyerhaeuser clearcut set-aside land under a shifting logging schedule.

Timeline

  1. January 2026: The $950 million transmission line went online.

  2. 2026: The original forest management plan was approved.

  3. September: The Department of Environmental Protection recommended the board reject the appeal.

  4. November 19, 2026: The board delayed a decision again and sent the plan back to staff.

Utilities Oversight

The board's repeated delays follow the transmission line's January 2026 start of operations, which left the forest conservation conditions as the main unfinished obligation. The dispute shows how state environmental conditions can outlast a project's energization, shaping how Maine balances clean-energy transmission against forest management.

Maine residents who rely on western forests for recreation or who live near the transmission corridor face unresolved rules on which stands can be cut. Electricity customers in Massachusetts depend on a line whose forest conditions remain under review.

The takeaway

Watch for the revised forest conservation plan from the Department of Environmental Protection, since its final terms will determine how much mature forest in western Maine is protected from harvest.

Further reading

Explore more Utilities coverage tied to Maine's energy and forest policy decisions.

Source note: This article includes information reported by Kennebec Journal and Morning Sentinel.