Daytime Paving Work Will Begin on Route 1A

Maine transportation crews will shift to daytime operations for highway preservation starting on September 28.

Updated on Sept. 27, 2026 in Current Conditions

An industrial paving machine parked on a rural highway shoulder, framed by evergreen trees under an overcast sky.
Maine Department of Transportation crews will begin daytime paving and drainage operations on a 2.79-mile stretch of Route 1A on September 28. AI Illustration. Upload story photo >

Live Poll

Do you plan to change your daily commute route due to ongoing road construction projects?

The Maine Department of Transportation will initiate daytime paving and drainage work on Route 1A beginning September 28. This effort is part of a larger highway preservation project spanning 2.79 miles through the area.

Why it matters

This construction project addresses necessary infrastructure maintenance by improving both drainage systems and roadway safety. These upgrades are intended to ensure the long-term integrity of a heavily traveled state route.

The $2,673,857.80 preservation project covers 2.79 miles of Route 1A. Crews are actively working on a section of roadway that begins 0.24 miles from the Holden town line.

The players

Maine Department of Transportation

This state agency is responsible for the oversight and management of highway infrastructure and public transit throughout Maine.

Eurovia Atlantic Coast/Northeast Construction

This firm is the contracted construction company managing the current paving and drainage operations on Route 1A.

The details

Contractors are paving the center turn lane alongside the left and right travel lanes to modernize the surface. While one of the three lanes undergoes paving, the department is maintaining two-way traffic in the remaining two lanes.

Timeline

  1. August 2: Night work began on the project.

  2. September 28: Daytime project work begins.

  3. October 2: Daytime work will continue until this date.

  4. October 23: Night work will conclude.

Seasonal Patterns

This project follows the maintenance standards and resource allocation protocols established by the Maine Department of Transportation's Highway Preservation Program. Such work reflects the standard cycle of infrastructure repair performed in Maine before the onset of winter conditions.

Commuters should prepare for potential traffic shifts as crews work between 8:30 a.m. and 3:30 p.m. Motorists are advised to navigate with caution through the construction zone, where two of three lanes will remain open for two-way traffic.

The takeaway

Maintaining key corridors like Route 1A requires balancing long-term infrastructure health with the immediate needs of daily commuters. Travelers should check local transit alerts for real-time adjustments to traffic patterns throughout October.