State Awards $38.6M Key Bridge Demolition Contract

Joseph B. Fay Company will handle demolition and marine work for the rebuild of the Francis Scott Key Bridge in Maryland.

Updated on Nov. 19, 2026 in Industry

State Awards $38.6M Key Bridge Demolition Contract

The Maryland Transportation Authority awarded a $38.6 million contract to the Joseph B. Fay Company for demolition and miscellaneous marine work tied to the Francis Scott Key Bridge rebuild. The award follows the state's April exit from its contract with Kiewit.

Why it matters

The procurement moves the Key Bridge rebuild forward after the state changed course on its contracting approach. Splitting the project into multiple contracts shapes how the state manages cost and schedule for a major Maryland infrastructure project.

The Maryland Transportation Authority awarded a $38.6 million contract to Joseph B. Fay Company, and the state will seek four separate procurement contracts across the bridge's phases. Three other procurements are being advanced while construction is underway.

The players

Joseph B. Fay Company

A contractor selected by the Maryland Transportation Authority to perform demolition and marine work on the Key Bridge rebuild.

Kiewit

A large construction and engineering firm that executed the design of the new Key Bridge before the state exited its contract in April 2026.

The details

The contract covers demolition and miscellaneous marine work for the rebuild of the Francis Scott Key Bridge, which collapsed in a fatal incident in March 2024. Kiewit had executed the design of the new bridge before the state exited that contract in April.

Timeline

  1. March 2024: The Key Bridge collapsed in a fatal incident.

  2. April 2026: The state exited its contract with Kiewit.

  3. November 19, 2026: The Maryland Transportation Authority awarded the $38.6 million demolition contract to Fay.

  4. Later this fall: Demolition and marine work is expected to begin.

Industry Context

The rebuild of the Francis Scott Key Bridge, collapsed in March 2024, has moved from the design phase executed by Kiewit toward physical demolition and marine work. The state's decision to split the project into four separate procurement contracts marks a departure from a single-contractor approach.

Commuters and drivers who rely on the Key Bridge corridor can expect construction activity to ramp up as demolition work begins later this fall. The phased procurement approach means project milestones may arrive in stages rather than all at once.

The takeaway

The Key Bridge rebuild is shifting from design into physical work, and the state's multi-contract approach will determine how quickly each phase moves forward.

What happens next

Demolition and marine work under the new contract is expected to begin later this fall.