MBTA Drawbridge Project Begins Construction at North Station
The $1.3 billion Draw One replacement will swap aging bridges for six-track vertical lift spans by 2032.
Updated on Nov. 25, 2026 in Construction

Skanska Civil Northeast/Koch joint venture began construction in May on the $1.3 billion North Station Draw One Bridge Replacement, a project of the Massachusetts Bay Transportation Authority. The work replaces two 95-year-old bascule spans with two vertical lift spans carrying six tracks.
Why it matters
Roughly 11 million passengers cross the drawbridges annually, and the bridge accommodates nearly 3,000 marine vessels each year, so the project affects both commuter rail service and Charles River boat traffic in Boston. The MBTA has committed to completing the work by summer 2029, while the project is set to finish by 2032 with no service interruption.
The project carries a $1.3 billion price tag, with the Skanska design saving the Commonwealth $140 million, and it will replace eight miles of commuter rail track and install 67 track specials. Whether the summer 2029 completion target will be met is not yet established.
The players
Massachusetts Bay Transportation Authority
The MBTA is the public agency that operates Boston's subway, commuter rail, bus and ferry services, and it is the owner and sponsor of this bridge replacement.
Skanska USA Civil
Skanska USA Civil is the U.S. civil construction arm of the Swedish multinational Skanska, and it leads the Skanska Civil Northeast/Koch joint venture building the project.
The details
The Skanska team, with VHB as designer, received approval for a two-bridge design with three-track lift spans for each, replacing the existing 95-year-old four-track rolling-lift bascule spans. The team must keep the tracks active 24/7 over the river throughout the job, and the project will also construct a new train control tower.
Timeline
1984: Remnant bascule bridges were destroyed by fire.
2018: A temporary control tower was built to replace an unsafe tower.
2024: The MBTA received a $472 million federal grant.
May 2026: Construction on the bridge project began.
Summer 2029: MBTA committed completion target.
Market Landscape
The project is financed in part by a $472 million grant from the U.S. Department of Transportation's National Infrastructure Project Assistance program, awarded in 2024. It places a major Boston commuter rail rebuild within the federally backed infrastructure funding that supports large transit projects across the country.
Commuter rail riders on the affected lines will face construction over the coming years, though the project is set to finish with no service interruption. Boaters on the Charles River should expect temporary closures, with maximum boat traffic closure of five days cited in the project materials.
The takeaway
Large transit projects like this one are often built around live service, so schedule commitments and service continuity are the key measures to watch as construction proceeds. Riders and boaters can track the 2029 and 2032 milestones to see whether the work stays on course.
Further reading
For more on regional building work, see Construction coverage in Boston.
Source note: This article includes information reported by Engineering News-Record (ENR) magazine.