The Federal Transit Administration has approved the Massachusetts Bay Transportation Authority's $4.08 billion Green Line Transformation Core Capacity Program for its Engineering Phase. Federal Capital Investment Grant funding is capped at $2.04 billion, or 50% of total project cost.
Why it matters
The Green Line currently carries about 94,700 riders daily on a system at capacity, and the program is slated to increase line capacity by roughly 37%. The approval also comes as the FTA proposes modernized evaluation criteria for 47 transit projects, a change that could affect how similar projects are funded.
The program carries a $4.08 billion price tag, with a federal Capital Investment Grant capped at $2.04 billion, or 50% of the total. The MBTA ordered 102 Type 10 cars from CAF in 2022 at a cost of $810 million, and the project will buy 56 higher-capacity vehicles and modify 27 stations.
The players
Massachusetts Bay Transportation Authority
The MBTA is the public agency that operates transit service across the Boston region, including the Green Line.
Federal Transit Administration
The FTA is the U.S. Department of Transportation agency that administers federal funding for public transit projects.
American Public Transportation Association
APTA is a national trade group representing public transit agencies, which filed comments challenging the proposed federal guidance.
CAF
CAF, or Construcciones y Auxiliar de Ferrocarriles, is a Spanish rail vehicle manufacturer that supplies the MBTA's Type 10 cars.
The details
The program upgrades power and legacy signal systems to support continuous operations across existing and new fleets, reconfigures four vehicle maintenance facilities and yards, and modifies 3.14 miles of track. It stays within the existing transit corridor and requires no additional right-of-way acquisition, and the new Type 10 cars will replace the Kinki Sharyo Type 7 and AnsaldoBreda Type 8 vehicles.
Timeline
2022: MBTA ordered 102 Type 10 cars from CAF.
November 17, 2026: APTA filed formal comments challenging the proposed CIG guidance.
November 21, 2026: FTA reported approval of the Green Line program for its Engineering Phase.
2027: MBTA is expected to begin receiving Type 10 cars.
Transit Funding Shift
The Green Line approval sits within the FTA's Capital Investment Grant pipeline, which the agency is now proposing to update through modernized evaluation criteria applying to 47 New Starts, Core Capacity and Small Starts projects. APTA's challenge to that proposed guidance signals that how federal transit dollars are allocated remains contested across the industry.
Riders on the Green Line should expect capacity gains of roughly 37% once the upgraded vehicles and signal systems are in service, though the cars are not expected until 2027. The program stays within the existing corridor, so the upgrades are not expected to require new property acquisitions along the route.
The takeaway
Federal capacity funding is shifting toward projects that can expand service within existing corridors, as the Green Line program shows. The 37% capacity gain shows what targeted upgrades to power, signals and vehicles can deliver without new right-of-way.
Further reading
For related coverage, see the Transportation section for more on how federal transit funding shapes regional projects.
Source note: This article includes information reported by Railway Track and Structures.
Live Poll
Do you think public transit in your area is getting better or worse?