SWBNO Plans Steel Plates Over Six-Foot Orleans Hole
The New Orleans utility says steel plates are expected the week of November 18 to cover a hole with damaged drain and sewer lines.
Updated on Nov. 19, 2026 in City Hall

Live Poll
Do you trust your local government to fix public hazards quickly?
The Sewerage and Water Board of New Orleans plans to cover a hole nearly six feet deep on Orleans Avenue with steel plates, according to General Superintendent Kaitlin Tymrak, who told city councilmembers on November 18. The utility identified damage to a drain line and a sewer line at the site.
Why it matters
The hole sits in a parking area near the American Can Apartments, and its repair affects residents and drivers in the area while the utility works through its backlog. The utility's dashboard shows an average repair timeline of 36 days, which indicates how long a fix at the site could take.
The SWBNO work order was opened November 12 and the utility expects steel plates the week of November 18. The hole could be filled by mid-December, though the timeline is an estimate based on the 36-day average and not a confirmed completion date.
The players
Sewerage and Water Board of New Orleans
The city utility responsible for drinking water, drainage and sewer service in New Orleans, which is handling the repair at the Orleans Avenue hole.
Kaitlin Tymrak
The General Superintendent of the Sewerage and Water Board of New Orleans, who briefed city councilmembers on the steel plate plan.
Aimee McCarron
A New Orleans city councilmember who met with Fox 8 about the hole on November 9.
The details
The hole is surrounded by gravel, flags and orange cones and is covered by wooden planks in the parking area along Orleans Avenue. Crews are prioritizing work at the location to complete necessary repairs, and councilmember Aimee McCarron met with Fox 8 about the hole on November 9.
Timeline
November 9: Councilmember Aimee McCarron meets with Fox 8 about the hole.
November 12: SWBNO opens a work order for the repair.
November 17: SWBNO releases a statement identifying drain and sewer line damage.
November 18: Tymrak tells council steel plates will be placed over the hole.
Mid-December: The hole could be filled, based on the average repair timeline.
City Hall Context
The 36-day average on the Sewerage and Water Board's public dashboard gives the Orleans Avenue repair a published benchmark against which its progress can be measured.
Residents and drivers near the American Can Apartments on Orleans Avenue will see the hole covered with steel plates before it is fully filled. The repair is a public safety matter for pedestrians and vehicles using the parking area during the work.
The takeaway
A public repair dashboard can show whether a utility's work is on pace, so residents can compare an active fix against the stated average timeline. The Orleans Avenue hole will be a measurable test of that schedule.
What happens next
SWBNO expects steel plates the week of November 18 and says the hole could be filled by mid-December.
Further reading
Explore more City Hall coverage on how New Orleans officials are tracking infrastructure repairs.
Source note: This article includes information reported by Fox8live.
Live Poll
Do you trust your local government to fix public hazards quickly?