Decatur Street Construction Project Completes
The Sewerage & Water Board finished the 15-month replacement of 115-year-old water mains in the Lower French Quarter after rolling closures and business losses.
Updated on Nov. 11, 2026 in Construction

Live Poll
Do you trust the city to manage major street projects without hurting local businesses?
The Sewerage & Water Board has completed the Decatur Street construction project in New Orleans, which lasted 15 months and replaced water transmission mains between Esplanade Avenue and Dumaine Street. At least three businesses shut down along the corridor during the work.
Why it matters
The federally funded project replaced 115-year-old water transmission mains with newer, larger pipes, addressing aging infrastructure beneath one of the city's busiest historic corridors. The city set up a fund to assist businesses affected by the disruption.
The project ran 15 months against an original completion target of August 2026, replacing mains that were 115 years old. Three businesses closed along the corridor, and the extraction does not report the total cost or final tally of affected businesses.
The players
Sewerage & Water Board
The Sewerage & Water Board is New Orleans' public utility agency responsible for drinking water, wastewater and drainage across the city.
The details
Crews replaced the water transmission mains on Decatur Street between Esplanade Avenue and Dumaine Street, with work on the final Esplanade-bound lane between Dumaine and St. Philip streets beginning in October 2026. Rolling closures affected the 900-1100 blocks of Decatur Street and the 600 block of St. Peter Street, and fencing removal was set to conclude Wednesday.
Timeline
August 2026: Project was originally scheduled for completion.
October 2026: Work began on the final stretch between Dumaine and St. Philip streets.
Tuesday, November 11, 2026: The Sewerage & Water Board announced completion on social media.
Wednesday, November 12, 2026: Fencing removal operations were scheduled to conclude.
Roadmap
Replacing mains more than a century old reflects a broader push to upgrade the buried water systems many older American cities depend on. Projects like this one typically trade long periods of street disruption for reduced risk of failures in the underlying network.
Drivers and pedestrians in the Lower French Quarter should expect that the rolling closures on Decatur Street and St. Peter Street have ended with fencing removal. Residents and visitors can now use the corridor again following the project's completion.
The takeaway
Long-running infrastructure projects can impose real costs on small businesses even when they deliver lasting public benefits. Monitoring city assistance programs can help affected owners recover after disruptions like this one.
Further reading
For more on local building and infrastructure work, see Construction coverage in New Orleans.
Live Poll
Do you trust the city to manage major street projects without hurting local businesses?










