Council Approves Phase Three of Mid-City Redevelopment

The Lake Charles City Council unanimously backed a $40 million Choice Neighborhood project featuring 62 mixed-income apartments in Mid-City.

Updated on Nov. 5, 2026 in City Hall

Council Approves Phase Three of Mid-City Redevelopment

Live Poll

Should your city use General Fund money to help build mixed-income housing?

The Lake Charles City Council voted unanimously to approve phase three of the Choice Neighborhood Initiative in Mid-City, a project that includes 62 mixed-income apartments and 3,600 square feet of retail space. The development is funded by a $40 million Choice Neighborhood grant, with the city contributing a loan of up to $1.5 million from its General Fund.

Why it matters

The city loan helped the project meet financial feasibility requirements needed to secure 9% housing tax credits after HRI Communities reduced the required loan amount to fill a financing gap. The development is intended to bring mixed-income housing and local retail space to the Lake Street corridor in Mid-City, Lake Charles.

The city loan carries a 0% interest rate, a second lien position and a 55-year term, with repayment drawn from 50% of available surplus cash flow. A $15 million tax credit reservation could be rescinded if the project does not close by the end of the year.

The players

HRI Communities

HRI Communities is the developer responsible for repaying the city loan and building the Mid-City Commerce project.

Lake Charles City Council

The Lake Charles City Council is the municipal governing body that voted to approve phase three of the Choice Neighborhood Initiative.

The details

The project includes 22 replacement units that prefer former residents of Lloyd Oaks and Dixie Drive. Debt service on the city loan begins the year after project stabilization, and HRI Communities must repay the loan over the 55-year term.

Timeline

  1. Closing is scheduled for December 2026.

  2. Construction is set to begin in January 2027.

  3. Construction is scheduled to finish in early 2028.

Policy Context

Phase three extends the Choice Neighborhood Initiative into Mid-City, pairing a $40 million federal grant with local financing to rebuild housing and commercial space in the area.

The project adds 62 mixed-income apartments and 3,600 square feet of ground-floor retail to the Lake Street corridor, creating new housing and local business space for Mid-City residents. Residents displaced from Lloyd Oaks and Dixie Drive are given preference for the 22 replacement units.

The takeaway

The project shows how a modest city loan can close a financing gap that determines whether a large federal housing grant turns into finished apartments and retail space. Its December closing deadline makes the timing of local financing decisions a practical concern for residents watching the Mid-City redevelopment.

What happens next

The Mid-City Commerce development is scheduled to close in December 2026, with construction slated to begin in January 2027 and finish in early 2028.

Further reading

For more on local government decisions, see City Hall coverage in Lake Charles.

Source note: This article includes information reported by Kplctv.

Live Poll

Should your city use General Fund money to help build mixed-income housing?