State-approved pumping is removing about 7 billion gallons of White River flood water that filled the company's Carmel, Indiana limestone quarry.
Updated on Nov. 18, 2026 in Emergency Response

Martin Marietta is pumping floodwater out of its Carmel, Indiana limestone quarry after a historic White River flood filled the site with roughly 7 billion gallons of water. Operations stopped and equipment was left submerged.
Why it matters
The flood breached a levee, eroded nearby land, destroyed a bridge and carried away soil, mature trees and part of a parking lot. Pumping is expected to take months, shaping how quickly the site and surrounding area can recover in Carmel.
The state-approved maximum pumping rate of 72,000 gallons per minute is set against roughly 7 billion gallons of water in the quarry, a volume that would take about two months of continuous pumping at that rate. Martin Marietta has not yet said which equipment survived the flood, and pumping rates will be adjusted as water levels fall.
The players
Martin Marietta
Martin Marietta is a major American construction materials company that operates aggregate and limestone quarries across the United States.
The details
The White River first pushed water backward along Bluewoods Creek, and a levee was breached, flooding the quarry and eroding nearby land. Pumping capacity was increased in stages under state approval, and water is discharged back toward the river through three pipelines that cross a closed stretch of Hazel Dell Parkway. The quarry also continues to take in water from Bluewoods Creek and groundwater.
Timeline
Nov. 10: State approval raised pumping capacity to 72,000 gallons per minute.
September: Martin Marietta warned state officials that pumping rates could change.
Wednesday: Pumping equipment and discharge pipes were filmed crossing closed Hazel Dell Parkway.
Seasonal Patterns
The staged increases in approved pumping capacity, from 5,000 to 48,000 and then 72,000 gallons per minute, follow the state's step-by-step approval process for flood-affected sites. The flood itself reached a crest of 26 feet on the White River, a level that ranks the event among the river's significant high-water episodes in the local record.
Residents near Hazel Dell Parkway should expect the road to remain closed while pumping equipment and discharge pipes are in place. Drivers should follow posted detours and avoid the closed stretch until officials reopen it.
The takeaway
Large flood-related industrial sites take months to dry out, so nearby residents should watch for road closures and changing pumping schedules. Staged approvals mean recovery timelines can shift as water levels drop.
Further reading
For more on how flood recovery is handled locally, see Emergency Response coverage in Carmel.
Source note: This article includes information reported by The Cool Down.