IDOT Finishes College Avenue Projects in Bloomington, Normal

Two College Avenue reconstruction projects on Illinois' west side were completed, part of the state's Rebuild Illinois capital plan.

Updated on Nov. 20, 2026 in Industry

Wide view of a newly rebuilt two-lane road with fresh concrete curbs running across flat Illinois prairie toward a rail crossing, part of a state highway upgrade.
The Illinois Department of Transportation finished a $16 million reconstruction of College Avenue in Bloomington and a $1.5 million project in Normal, both funded under the state's Rebuild Illinois capital plan. AI Illustration. Upload story photo >

Live Poll

Do you think road conditions in your area are getting better?

The Illinois Department of Transportation completed a $16 million reconstruction of College Avenue from Rivian Parkway to the Norfolk Southern tracks in Bloomington, and a $1.5 million project from U.S. 150 to White Oak Road in Normal. Both projects were funded under the state's bipartisan Rebuild Illinois capital plan.

Why it matters

The Normal corridor was outdated and has been modernized, adding to the statewide effort to upgrade highways and bridges across Illinois. The work comes as Rebuild Illinois enters its sixth year.

The Bloomington project cost $16 million and the Normal project cost $1.5 million, within a Rebuild Illinois program that has spent $20.8 billion on highways and bridges statewide. Whether either project came in on or against its original budget is not addressed in the source.

The players

Illinois Department of Transportation

The state agency responsible for planning, building and maintaining Illinois' highways, bridges and other transportation infrastructure.

The details

The Bloomington project reconstructed College Avenue from Rivian Parkway east to the Norfolk Southern tracks, adding new storm sewers, curbs and gutters, and began in 2024 before completion on October 31. The Normal project reconstructed College Avenue from U.S. 150 to White Oak Road, breaking ground in March 2026 and finishing November 15, 2026.

Timeline

  1. 2024: Bloomington College Avenue project started.

  2. March 2026: Normal College Avenue project broke ground.

  3. October 31, 2026: Bloomington College Avenue project completed.

  4. November 15, 2026: Normal College Avenue project completed.

  5. Winter 2028: Four ongoing Illinois Route 9 projects expected to finish.

Roadmap

Both College Avenue projects were funded under the Rebuild Illinois capital plan, now in its sixth year and having spent $20.8 billion on highways and bridges statewide. They extend that program's modernization work into the Bloomington-Normal corridor.

Drivers using College Avenue in Bloomington and Normal now have reconstructed roadway with new storm sewers, curbs and gutters, which the state says improves the corridor. Motorists on Illinois Route 9 should expect ongoing construction, with those four projects expected to wrap up in winter 2028.

The takeaway

Modernized corridors like this one reflect how statewide capital programs translate into local road improvements. Residents driving these routes can expect smoother pavement and improved drainage, while Route 9 work continues through 2028.

Further reading

For more on statewide road and bridge work, see Construction coverage across Illinois.

Source note: This article includes information reported by Wglt.