Waterloo Extends Data Center Moratorium to April

The City Council unanimously approved a four-month extension of its temporary ban on data center development.

Updated on Nov. 22, 2026 in Data Centers

Bold flat-color editorial illustration of a windowless gray data center block on open fenced land beside a cluster of cooling units, in slate and cream with a muted red accent.
Waterloo City Council unanimously voted Tuesday to extend its temporary data center development ban by four months, to April 20, while officials craft zoning rules after a $1 land sale to Wahawk Power LLC. AI Illustration. Upload story photo >

Live Poll

Should your city allow a large data center to be built nearby?

Waterloo City Council unanimously approved extending its temporary data center development ban by four months, to April 20. The original 90-day moratorium, passed Sept. 8, was set to expire Dec. 7.

Why it matters

The extension gives the city more time to craft zoning rules after a $1 land sale to Wahawk Power LLC drew opposition from residents and officials. Councilmember Steve Simon said more information became available and the issue became a nationwide concern after the sale was approved.

The moratorium runs four months versus the original 90-day term, and the proposed data center would be 80,000 square feet on 12 acres. A petition with more than 3,500 signatures opposed the project, but the outcome of the zoning review remains unresolved.

The players

Waterloo City Council

The elected body of Iowa's Waterloo that approved the moratorium extension and the land sale to the developer.

Dave Morrow

Ward 2 Waterloo councilmember who proposed the data center moratorium after research with city departments and utility providers.

Mark Nelson

Woodbury County supervisor who said 16 cameras were installed on county right-of-way around Salix without permission.

The details

The moratorium prohibits the city from accepting, processing, approving or issuing any development agreement for a data center, and also covers substantial expansion or conversion of existing buildings. Councilmember Dave Morrow proposed the moratorium, which was researched with city departments and utility providers; the land sale gives the developer an option to buy 10 to 12 more acres for $1 within five years.

Timeline

  1. Dec. 15 (prior year): Council unanimously approved the $1 land sale to Wahawk Power LLC.

  2. Sept. 8 (prior year): The original 90-day moratorium was passed.

  3. Nov. 23: First public informational meeting, 4 to 6 p.m.

  4. Dec. 3: Second public informational meeting, 4 to 6 p.m.

  5. Dec. 7: Staff will present an updated draft at a council work session.

Market Landscape

Waterloo's temporary pause follows a pattern of local governments halting data center approvals while drafting zoning rules for large facilities. The city's review of a mid-size, 80,000-square-foot project contrasts with the hyperscale facilities that have driven most recent local debate.

Residents can review the city's draft data center zoning ordinance and the public meeting materials to understand the rules that may apply to future projects. The moratorium means no new data center development agreements can be approved in Waterloo until the pause ends in April.

The takeaway

Residents who want to influence the outcome can attend council work sessions and submit comments on the draft zoning rules before the moratorium ends in April. Following the Dec. 7 work session will show how public input shapes the final ordinance.

What happens next

Staff will evaluate public meeting input and present an updated draft zoning ordinance at a council work session on Dec. 7.

Further reading

Explore more on Data Centers coverage affecting Waterloo communities.

More information

Read the city's draft data center zoning ordinance on the City of Waterloo website.

Source note: This article includes information reported by Sioux City Journal.