Cedar Rapids Will Close Bridge of Lions to Traffic
The 16th Avenue Bridge of Lions closes to all vehicles starting October 5, 2026, for flood-control upgrades.
Updated on Oct. 2, 2026 in Openings & Closings

Live Poll
Do you support the temporary closure of main transit routes for necessary flood-control infrastructure improvements?
The city of Cedar Rapids will close the 16th Avenue Bridge of Lions to vehicle traffic beginning October 5, 2026. This closure is scheduled to last for approximately 12 weeks to accommodate planned flood-control improvements.
Why it matters
The closure is necessary to facilitate critical infrastructure work aimed at enhancing flood protection for the surrounding area. Upgrading these flood-control measures remains a priority to ensure long-term safety for the local community.
The bridge closure is projected to last 12 weeks to complete the necessary infrastructure upgrades. This timeframe includes the removal of the bridge's arch façade.
The players
City of Cedar Rapids
The municipal government overseeing the infrastructure maintenance and flood-control projects for the city.
The details
Vehicle traffic will be prohibited between A Street SW and Second Street SE throughout the construction period. While the bridge closes to cars, a single pedestrian lane will remain accessible to the public, though brief closures will occur during scheduled flood-gate exercises.
Timeline
October 5, 2026: 16th Avenue Bridge of Lions closes to vehicles.
Market Landscape
This project follows a pattern set by the Cedar Rapids flood-control improvements. It represents a larger trend of municipal investment in infrastructure to mitigate environmental risks in urban areas.
Commuters will need to identify alternate routes between A Street SW and Second Street SE for the 12-week duration. Pedestrians can still cross the bridge using the remaining open lane, except during times when flood-gate exercises cause brief closures.
The takeaway
Drivers are encouraged to plan for potential congestion on surrounding routes during the 12-week closure period. Pedestrians should check city notices to avoid potential delays during scheduled flood-gate testing.
Further reading
For more information on local infrastructure changes, visit the Openings & Closings section.
Source note: This article includes information reported by KGAN.
Live Poll
Do you support the temporary closure of main transit routes for necessary flood-control infrastructure improvements?










