ONE Nuclear Advances 1,000-MW Iowa Plant Plans
The Northern Pike project would use a small modular reactor in Cerro Gordo County, with transmission access still being explored.
Updated on Nov. 19, 2026 in Science

Live Poll
Should Iowa build new nuclear power plants to meet growing electricity demand?
ONE Nuclear Energy Inc. has advanced plans for a 1,000-MW nuclear power project in Cerro Gordo County, Iowa. The company signed a letter of intent with SOO Green on November 5 to explore transmission access to the PJM grid, though the letter does not reserve transmission capacity.
Why it matters
The project is intended to supply dependable power for growing industrial and computing demand in the region. For Iowa, it arrives as the state adopts new incentives for nuclear generation and weighs its long-term energy mix.
ONE Nuclear's plan calls for a 1,000 MW small modular reactor, and the proposed SOO Green HVDC Link would carry up to 2,100 MW over roughly 350 miles at ±525 kV. Whether that transmission capacity will be secured for the project has not been determined.
The players
ONE Nuclear Energy Inc.
A nuclear developer pursuing the Northern Pike small modular reactor project in Iowa, the company is advancing plans for a 1,000-MW facility.
SOO Green
A transmission developer proposing the SOO Green HVDC Link, an open-access line intended to connect Iowa generation to electricity markets in Illinois and the PJM region.
The details
ONE Nuclear and SOO Green signed a letter of intent to explore potential transmission access for Project Northern Pike. The project is evaluating battery storage and a hybrid cooling concept, and the line would be operated as an open-access facility serving multiple generation resources and electricity buyers.
Timeline
September 2026: Iowa's Nuclear Energy Task Force issued nine recommendations.
July 1, 2026: Iowa's sales and use tax exemptions for qualifying nuclear generation facilities took effect under House File 2757.
November 5, 2026: ONE Nuclear and SOO Green signed their letter of intent.
Q4 2032 through Q3 2033: SOO Green's updated target in-service window for the transmission line.
Mid-2030s: ONE Nuclear is targeting first generation at Northern Pike.
Roadmap
Iowa enacted House File 2757 to offer sales and use tax exemptions for qualifying nuclear generation facilities, and ONE Nuclear's Northern Pike plan is one of the projects positioned to draw on that state policy shift. The proposal also reflects a wider effort to pair new firm generation with dedicated long-distance transmission.
If built as planned, the project could add firm generation to the regional grid, with first output targeted for the mid-2030s. Iowa residents would see the effects through electricity supply and any future rate or land-use decisions tied to the project.
The takeaway
Large nuclear projects depend on transmission access as much as on reactor design, so the status of capacity reservations will be a key indicator of whether Northern Pike advances on schedule.
Further reading
For broader context on how states are shaping power supply, see the Energy section's coverage of Iowa Energy.
Source note: This article includes information reported by Constructionreview.
Live Poll
Should Iowa build new nuclear power plants to meet growing electricity demand?