Iowa Panel to Hear Hickory Grove Gas Plant Case

Central Iowa Power Cooperative's proposed 240-megawatt Scott County plant faces commission testimony next week after a local zoning rejection.

Updated on Nov. 13, 2026 in Utilities

Iowa Panel to Hear Hickory Grove Gas Plant Case

Live Poll

Should a natural gas power plant be built near your community?

The Iowa Utility Commission will hear testimony Tuesday, November 17, at 9 a.m. at the DoubleTree by Hilton in Davenport on Central Iowa Power Cooperative's proposed Hickory Grove Generating Station in Scott County. The Scott County Board of Supervisors unanimously rejected the thermal-energy zoning proposal needed for the plant's construction.

Why it matters

The commission will decide whether the 95-acre site in northwest Scott County is permissible, a proceeding separate from the local county board's zoning action. Residents of nearby Eldridge, Maysville and Donahue have raised environmental and health concerns about the plant's proximity to their communities.

The filing describes a 240-megawatt natural gas plant with a $400 million estimated cost on 95 acres in northwest Scott County. Commissioners have not yet ruled on whether the site is permissible, and the weight the commission will give the submitted interventional testimony remains unclear.

The players

Central Iowa Power Cooperative

A cooperative utility that proposed the Hickory Grove Generating Station and filed for its certificate of public convenience, use and necessity.

Iowa Utility Commission

A quasi-judicial state body whose commissioners are appointed by the governor to regulate Iowa utilities and decide on proposed generating facilities.

The details

Central Iowa Power Cooperative filed its application for a certificate of public convenience, use and necessity on May 19. Commissioners, appointed by the governor and acting in a quasi-judicial role, will hear witnesses in daily sessions until all testimony is presented. Meeting attendees questioned the project's claimed local job creation and alleged the cooperative's history of outsourcing construction.

Timeline

  1. May 19: CIPCO filed its certificate of public convenience application.

  2. Tuesday, November 17, 9 a.m.: Iowa Utility Commission hearings begin at the DoubleTree by Hilton in Davenport.

Industry Context

The proposal follows Iowa's state certificate of public convenience, use and necessity pathway, in which the Iowa Utility Commission decides siting independently of county zoning. Here the county has rejected the thermal-energy zoning the plant needs, so the state proceeding is now the decisive test.

Residents of Eldridge, Maysville and Donahue would live nearest a 240-megawatt gas plant if the commission permits the site, a consequence that bears directly on local air and health concerns. Those who want to weigh in can follow the commission's docket, where interventional testimony has already been submitted.

The takeaway

Watch the November 17 hearing if the Hickory Grove project affects your community, since the commission's ruling will set whether the 95-acre Scott County site can proceed regardless of the local zoning vote. Testimony submitted to the docket is part of the record the commission will weigh.

What happens next

The Iowa Utility Commission begins hearings Tuesday, November 17, at 9 a.m. at the DoubleTree by Hilton in Davenport, where it will take testimony on the Hickory Grove project.

Further reading

For background on the state agencies overseeing power projects, see Utilities coverage across Iowa.