Parsons Wins $45.7M Contract to Treat Pensacola Groundwater
The Army Corps of Engineers awarded the groundwater cleanup at the Escambia Wood Treating Co. Superfund site to Parsons Government Services.
Updated on Nov. 20, 2026 in Environmental

Parsons Government Services won a $45.7 million U.S. Army Corps of Engineers contract to treat groundwater at the Escambia Wood Treating Co. Superfund site in Pensacola. The firm-fixed-price, indefinite-delivery/indefinite-quantity award covers the site's second operable unit, which addresses groundwater.
Why it matters
The site's wood treatment operations and wastewater ponds introduced contaminants that reached the aquifer, and the contract advances cleanup of a plume that extends toward Bayou Texar in Pensacola. Groundwater work has followed decades of soil remediation completed in 2010.
The groundwater treatment uses in situ thermal treatment and in situ chemical oxidation, with naphthalene serving as the principal contaminant EPA uses to map the plume roughly 1.5 miles east-southeast of the site. Work locations and funding will be set with each order under the contract.
The players
Parsons Government Services
Parsons Government Services is a federal contractor that won the groundwater treatment award for the Escambia Wood site.
U.S. Army Corps of Engineers
The U.S. Army Corps of Engineers is the federal agency that awarded the contract and manages the cleanup under the Superfund program.
U.S. Environmental Protection Agency
The U.S. Environmental Protection Agency oversees the Superfund program and allocated $40 million for groundwater work from the Infrastructure Investment and Jobs Act.
The details
The contract covers the second operable unit at the site, which addresses groundwater, while soil remediation was completed in 2010. The Escambia site pressure-treated wood from 1942 until it closed in 1982, and EPA excavated roughly 225,000 cubic yards of contaminated soil in 1991 and 1992.
Timeline
1942: Wood treatment operations begin at the Escambia site.
1982: Escambia Wood site closes.
1991 and 1992: EPA excavates roughly 225,000 cubic yards of contaminated soil.
December 1994: EPA adds the site to the National Priorities List.
November 18, 2031: Estimated completion date of the groundwater contract.
Legacy Cleanup
The award puts part of the $40 million EPA groundwater allocation from the Infrastructure Investment and Jobs Act to work at a Superfund site that was listed on the National Priorities List in December 1994. It follows the earlier soil excavation of roughly 225,000 cubic yards in 1991 and 1992 and the $1 billion Superfund investment EPA announced in December 2021.
Residents near Bayou Texar and the former Escambia Wood property in Pensacola should watch for project notices as work orders are issued under the contract. The contract's estimated completion date is November 18, 2031, so cleanup activity is expected to continue well beyond the award.
The takeaway
Long-running Superfund sites often require multiple phases of cleanup, and the Escambia Wood case shows soil work finishing before groundwater treatment begins. Tracking contract awards and estimated completion dates can help the public follow whether that work proceeds on schedule.
Further reading
Explore more Environmental coverage for context on cleanup efforts like this one.
Source note: This article includes information reported by ExecutiveBiz.






