Patti Marine Adds Floating Dry Dock at Bayou Chico

The 800-ton Amanda Joe dock, built with a federal matching grant, entered operation at the Pensacola shipyard.

Updated on Nov. 20, 2026 in Industry

Floating dry dock of grey steel moored in a calm coastal bayou beside a low barge, with green marsh and distant cranes at a Pensacola shipyard.
Patti Marine Enterprises added an 800-ton floating dry dock named Amanda Joe at its Bayou Chico yard in Pensacola, expanding repair capacity. AI Illustration. Upload story photo >

Patti Marine Enterprises has added an 800-ton floating dry dock to its Bayou Chico yard in Pensacola. The dock, named Amanda Joe, was launched down the yard's rail and moored to an existing spud barge, with its first job being repairs on the US Navy diving training boat Poseidon.

Why it matters

The dock expands the yard's capacity to service and restore existing vessels, which had been limited before. The company says the expansion could help it double in size over the next five years.

The dock measures about 36.6 by 20.4 metres and sits roughly 207 metres from the federal navigation channel, in a seabed depth range of 5.2 to 6.4 metres. The dock was built with a US$1.2 million MARAD matching grant, while the yard's prior rail system handled 1,200 tons.

The players

Patti Marine Enterprises

A Pensacola-based shipbuilding and repair company operating the Bayou Chico shipyard.

US Department of Transportation Maritime Administration (MARAD)

The federal agency within the US Department of Transportation that funds small shipyard development through its grant programs.

The details

The dock was built at the upland shipyard and launched using the existing rail system before being permanently tethered to the yard's 61- by 12.2-metre spud barge, with no new moorings, pilings or dredging proposed. Docking and undocking are planned for high tide to make use of the greatest available depth.

Timeline

  1. July 21, 2022: MARAD announced the FY2022 small shipyard grant awards, including the Patti Marine matching grant.

  2. April 2023: Patti's application to the US Army Corps of Engineers was published.

  3. July 2024: Frank Patti Jr. described the expansion to FloridaWest EDA.

  4. November 19, 2025: The company announced the dock had been launched and was operating.

Transportation Infrastructure Context

The dock was funded under the MARAD FY2022 Small Shipyard Grant Program, which allocated US$19.6 million across 24 small shipyards in 19 states. The Bayou Chico project shows how that federal program is being used to expand local repair capacity rather than only new construction.

The dock increases the yard's ability to haul out and repair vessels locally, which may shorten turnaround for commercial and government customers. Local maritime operators may see more repair capacity available in the Bayou Chico area.

The takeaway

Expanded local dry-dock capacity can reduce reliance on distant yards for vessel repairs. Maritime businesses in the Pensacola area may want to watch for shifts in service availability at Bayou Chico.

Further reading

For related coverage, see Transportation news from the Pensacola region.

Source note: This article includes information reported by Baird Maritime.