Devil's Gate Southeast Entrance to Close to Visitors

Los Angeles County begins a $3.3 million entrance improvement project at the Pasadena site on December 18.

Updated on Nov. 20, 2026 in National Parks

Gouache-painted editorial illustration of a wide walkway curving toward a concrete dam wall beside dry hillsides, with a freshly graded entrance ramp and open metal gate.
Los Angeles County begins a $3.3 million project on December 18 that will close the southeast entrance to Hahamongna Watershed Park at Devil's Gate Dam in Pasadena through June 2027. AI Illustration. Upload story photo >

Live Poll

Do you think local park construction projects are worth the temporary disruption?

The southeast entrance to Hahamongna Watershed Park at Devil's Gate Dam and Reservoir closes beginning December 18, 2026, while Los Angeles County Public Works carries out the Southeast Entrance Improvement Project. Construction is scheduled to continue through June 28, 2027, and visitors are directed to alternate entrances at Explorer Road and at Foothill Boulevard and Oak Grove Drive.

Why it matters

The project will create a wider, lower pedestrian walkway and a new ADA-compliant ramp, along with new fencing, gates, signage and pavement striping. Pasadena residents and park visitors will need to plan routes around the closure for roughly six months.

The county lists a total estimated project cost of $3,317,000, with a construction contract estimated at $1.2 million to $1.8 million. Work runs weekdays from 7 a.m. to 5 p.m. and does not take place on holidays or Rose Bowl event days, though the county cautioned the schedule could change.

The players

Los Angeles County Public Works

The county agency responsible for public infrastructure, including flood control facilities and park access projects across Los Angeles County.

The details

Redesigned walkways will connect the entrance to surrounding trails, and native landscaping will replace portions of the existing entrance area. Funding comes from the Los Angeles County Flood Control District, and the Board of Supervisors approved the project on June 9, 2026.

Timeline

  1. July 2020: Devil's Gate Reservoir Sediment Removal Settlement Agreement approved.

  2. June 9, 2026: Los Angeles County Board of Supervisors approves the project.

  3. November 19, 2026: Public Works distributes the closure notice.

  4. December 18, 2026: Southeast entrance closes to visitors.

  5. June 28, 2027: Scheduled construction completion.

Legal Context

The entrance work fulfills a commitment tied to the Devil's Gate Reservoir Sediment Removal Settlement Agreement approved in July 2020. It marks one of the agreement's concrete outcomes showing up at the park itself, rather than only in reservoir maintenance.

Visitors planning hikes at Hahamongna Watershed Park should use the Explorer Road or Foothill Boulevard and Oak Grove Drive entrances starting December 18, 2026. Avoid weekday mornings and afternoons when construction is active if you plan to drive to the alternate entrances.

The takeaway

Plan park visits around the alternate entrances for the next six months, and check the county's project updates before heading out. Schedules for public works projects can shift, so confirm access before a trip.

What happens next

Construction on the southeast entrance is scheduled to finish on June 28, 2027, with the county noting that this timeline could change.

Further reading

Explore more about National Parks in and around Pasadena for trail and park access context.

More information

Check county Devil's Gate southeast entrance project updates for the latest construction information.

Source note: This article includes information reported by Pasadena Now.

Live Poll

Do you think local park construction projects are worth the temporary disruption?