PG&E Halts Second Palo Alto Power Line Work
Palo Alto's city manager says PG&E has stopped work on a second transmission line meant to guard the city against long outages.
Updated on Nov. 18, 2026 in Business

Live Poll
Do you trust local utilities to keep your power reliable during outages?
PG&E has stopped work on a second power line to Palo Alto, according to the city manager, a project intended to protect the city from prolonged outages. The utility is also cutting 15% of next year's construction projects.
Why it matters
Palo Alto depends on a single corridor of transmission lines from the east, so a loss of that corridor could leave the city dark for an extended period. The project's delay adds risk for residents of Palo Alto while PG&E reduces construction spending.
PG&E is cutting 15% of next year's construction projects, while the planned second line would cost $40 to $80 million and is funded by utilities across the state. It is not yet known when work on the line will resume.
The players
PG&E
Pacific Gas and Electric Company is a major California utility that serves millions of customers across the state's northern and central regions.
Robert Rivas
Robert Rivas is the Speaker of the California State Assembly, the lower house of the state legislature.
Ed Shikada
Ed Shikada is the city manager of Palo Alto, responsible for the city's day-to-day administration.
The details
The city manager said PG&E stopped work on the second line, which would connect a PG&E substation at NASA Ames in Mountain View to a Palo Alto substation at Colorado Avenue and West Bayshore Road. The project follows the failure of Senate Bill 492, which would have reduced wildfire liability for utilities, after Assembly Speaker Robert Rivas declined to bring it to a vote on Sept. 1.
Timeline
Feb. 17, 2010: An airplane crashed into power lines in East Palo Alto, killing the pilot and two passengers.
Sept. 1, 2026: Assembly Speaker Robert Rivas declined to bring Senate Bill 492 to a vote.
Oct. 5, 2026: The city manager emailed the council about PG&E stopping work.
2029: Design work is expected after environmental review, which takes at least 18 months.
2034: The second transmission line is planned to enter service.
Season Trajectory
The second line is a direct response to the 2010 crash, which took out all three transmission lines running along a single corridor into Palo Alto. Because that vulnerability remains until the line is built, the delay extends the city's exposure to a repeat event.
Palo Alto residents remain dependent on a single transmission corridor until the second line is complete. If a similar event occurred today, the outage would likely last two or three days.
The takeaway
Grid redundancy projects can take years to finish, and delays in permitting or funding leave communities exposed to outages in the meantime.
Further reading
Explore more Utilities coverage for context on how grid projects are funded and delayed.
Source note: This article includes information reported by Palo Alto Daily Post.