Long Beach to Start Orange Avenue Bikeway in December
The nearly $30 million project adds about 5.5 miles of bicycle facilities and is slated for completion by late 2028.
Updated on Nov. 25, 2026 in Politics

Live Poll
Do you support Long Beach spending $30 million on the Orange Avenue bikeway?
Construction on a nearly $30 million Orange Avenue bikeway project in Long Beach is scheduled to begin in December. The City Council awarded the construction contract to Long Beach-based Excel Paving Co. on June 9.
Why it matters
The project is intended to strengthen a north-south connection between downtown Long Beach and North Long Beach and to close gaps in the city's bicycle network. Temporary traffic impacts and possible driveway-access restrictions are expected during some phases.
The project covers about 5.5 miles of bicycle facilities and is funded by the Active Transportation Program, Measure A, Measure M, Proposition A, Proposition C, and Transportation Development Act funds. Construction will proceed in phases with at least one traffic lane open at all times.
The players
Excel Paving Co.
A Long Beach-based paving contractor awarded the construction contract for the Orange Avenue bikeway project.
Long Beach City Council
The city's legislative body that awarded the construction contract on June 9 and oversees citywide public works projects.
The details
The project includes bike lanes, protected intersections, high-visibility crossings, traffic-signal modifications, expanded bus stops, pavement rehabilitation, sidewalk reconstruction and ADA-compliant curb ramps. It builds on prior work along Orange Avenue between 52nd and 72nd streets and along Alamitos Avenue between Ocean Boulevard and Seventh Street.
Timeline
June 9: City Council awarded the construction contract to Excel Paving Co.
December: Construction is set to begin on the Orange Avenue bikeway project.
Late 2028: Projected completion, barring unforeseen circumstances.
Roadmap
The project is funded in part by Measure A, Measure M, Proposition A and Proposition C, voter-approved Los Angeles County transportation sales taxes that have financed many local street and transit upgrades. It extends that county-funded approach to close gaps in Long Beach's bicycle network.
Drivers and bus riders along Orange Avenue should expect temporary lane and driveway changes during construction, though at least one traffic lane will remain open at all times. Cyclists will gain new bike lanes and protected intersections once the work is complete.
The takeaway
Residents who use Orange Avenue or the surrounding streets can plan for phased work and possible driveway restrictions over the next two years. Checking the city's project updates before commuting can help avoid delays.
What happens next
Construction on the Orange Avenue bikeway is scheduled to begin in December, with completion projected for late 2028.
Further reading
For more on local decisions behind projects like this, see the City Hall coverage.
More information
Follow Orange Avenue project construction updates on the City of Long Beach website for schedule changes.
Source note: This article includes information reported by My News LA.
Live Poll
Do you support Long Beach spending $30 million on the Orange Avenue bikeway?






