Long Beach to Begin El Dorado Nature Center Construction

Work at the Nature Center's Spring Street entrance and parking lot starts the week of November 30 as part of a broader El Dorado Park project.

Updated on Nov. 19, 2026 in Industry

Long Beach to Begin El Dorado Nature Center Construction

Live Poll

Would you support paying entry fees at El Dorado East Regional Park?

Long Beach will begin construction at the Spring Street entrance and parking lot of the El Dorado Nature Center the week of November 30. Parts of the regular parking lot and main Nature Center entry may be inaccessible at intermittent periods during the work.

Why it matters

The project is meant to create a safer, more accessible and enjoyable experience for visitors to the Nature Center and El Dorado East Regional Park. It is one phase of the El Dorado Park Paving, Wayfinding and Parking Management project, which is funded by California State Parks, the city's general fund and Measure A money.

Visitors may need to walk about half a mile from temporary parking across Spring Street to reach the alternate Nature Center entry. Construction at the Spring Street entrance is set to begin the week of November 30, but the total cost of the project was not included in the available information.

The players

City of Long Beach

The city government of Long Beach, California, which is managing the El Dorado Park improvements and the Elevate '28 Infrastructure Investment Plan.

California State Parks

The state agency that oversees California's state park system and is providing funding for the El Dorado Park project.

The details

Construction will take place at the Spring Street entrance and Nature Center parking lot, with a temporary ADA-compliant pathway installed at the alternate entrance. Visitors may be directed to park across Spring Street at the lot adjacent to the archery range inside El Dorado East Regional Park, Area 2, and use the designated crosswalk at Spring Street and El Dorado Park Street. Long Beach Animal Care Services and community garden visitors may still access those facilities through the normal entry.

Timeline

  1. Week of November 30, 2026: Construction begins at the Spring Street entrance and Nature Center parking lot.

  2. December 2026 to January 2027: Gate 1 construction is expected to last.

  3. End of 2026: Wayfinding signage work is expected to begin at El Dorado East Regional Park.

  4. Early 2027: Wayfinding signage work is expected to be complete.

  5. Spring 2027: The parking management system is expected to be completed at all four entry points.

Roadmap

The El Dorado Park work is one of the projects funded under Long Beach's Elevate '28 Infrastructure Investment Plan, which the city is using to modernize its public facilities. The park's paving, wayfinding and parking upgrades follow that plan's focus on updating aging infrastructure across the city.

Visitors should expect intermittent closures of the regular Nature Center parking lot and main entry during Gate 1 construction, which is expected to run from December to January. Those heading to the Nature Center may need to park across Spring Street and walk about half a mile to the alternate entrance.

The takeaway

Visitors planning trips to the Nature Center during the coming months should check the city's project page for closure updates and plan for a longer walk from temporary parking. The upgrades are intended to make arrival and navigation easier once the work is finished.

What happens next

Wayfinding signage work is expected to begin by the end of 2026 and be complete by early 2027, and the parking management system is expected to be finished at all four entry points in spring 2027.

Further reading

For more on local building projects, see Construction coverage for Long Beach.

More information

Find updates on the work at the City of Long Beach El Dorado Park improvement projects page.

Source note: This article includes information reported by Press Telegram.