Critical Loop Launches 25 MW Microgrid in Long Beach
Critical Loop's CLB-5100 Power System deploys a hybrid microgrid at an SRG Commercial campus in Southern California.
Updated on Nov. 19, 2026 in Industry

Critical Loop launched its CLB-5100 Power System with a 25 MW hybrid microgrid at an SRG Commercial campus in Southern California. The deployment is the first public application with SRG of Critical Loop's Power-Ready Industrial Portfolio model.
Why it matters
Regional utility energization did not align with the tenant's commercial operation date, and the SRG tenant, an advanced manufacturer, operates under an early 2027 deadline. The bridge solution is designed to cover that gap while the grid connection is completed.
The 25 MW system combines roughly 7 MW of firm grid capacity, a 2 MW flexible connection, 12 MW/60 MWh of battery storage and 3.5 MW of emergency generation. Whether energization will meet the tenant's early 2027 date has not been stated.
The players
Critical Loop
Critical Loop is a microgrid and power systems company that developed the CLB-5100 Power System and its Power-Ready Industrial Portfolio model.
SRG Commercial
SRG Commercial is a commercial real estate developer that hosts the Southern California campus where the microgrid was deployed.
The details
Battery storage is the primary means of power augmentation, with onsite generation filling remaining operational gaps. The system pulls additional headroom from the utility whenever power levels drop, and is designed to reach 25 MW within nine months from contract to energization.
Timeline
Early 2027: tenant's commercial operation deadline for the advanced manufacturer.
Nine months from contract: target for reaching 25 MW energization.
18 months: duration of the bridge hybrid power solution.
Two years: term of SRG's preferred microgrid partner agreement with Critical Loop.
Utility Context
The deployment is the first public application with SRG of Critical Loop's Power-Ready Industrial Portfolio model, extending that approach to a commercial campus. It positions bridge power as a way for developers to meet tenant deadlines while utility connections are still pending.
For Long Beach businesses and nearby residents, a bridge microgrid can keep commercial operations on schedule when grid connections lag. The approach also signals that tenants may see faster power availability in new developments.
The takeaway
When utility timelines slip, bridge power systems can keep new commercial projects on schedule. Businesses planning facility moves in Southern California should ask developers about interim power options.