Fresno Irrigation District Upgrades Canal Headgate

A portable dam built by a New Jersey company is holding back Kings River water while the district replaces its headgate gates.

Updated on Nov. 26, 2026 in Industry

Tarp-covered metal A-frames and sandbags hold back a shallow river channel beside a concrete canal headgate in a flat agricultural valley.
The Fresno Irrigation District hired Portadam, a New Jersey company, to hold back Kings River water with a portable dam while a $800,000 headgate upgrade is completed by Nov. 25. AI Illustration. Upload story photo >

Live Poll

Do you trust your local water district to spend public money wisely?

The Fresno Irrigation District has contracted New Jersey company Portadam to use a portable dam while it upgrades the main Kings River headgate on the Fresno Canal for $800,000. The headgate's epoxy-coated steel gates are being replaced with stainless steel motor-operated gates, with the project expected to be completed by Nov. 25.

Why it matters

The portable dam holds back water so crews can perform the headgate work, and it is less intrusive to the channel than a temporary cobble dam. The upgrade affects how water flows into the Fresno Canal serving the local irrigation district.

The $800,000 contract covers replacing the headgate's gates, which were built in 1905 and purchased by the district in 1920. A portable dam roughly 90 feet across and 10 feet high holds back water during the work, though the district has not said how the cost compares with earlier upgrades.

The players

Fresno Irrigation District

A public water agency that delivers irrigation water from the Kings River to farms around Fresno, and that owns and operates the Fresno Canal headgate.

Portadam

A New Jersey company that makes portable dams used to temporarily hold back water during infrastructure work.

The details

Crews are using a row of metal A-frames covered by a tarp and held by sandbags to block the Fresno Canal while the headgate is upgraded. The district's original headgate had custom cast iron gates later replaced with epoxy-coated steel, and two electric motors added more than eight decades ago controlled the gates in groups. Work began about a week before an Oct. 27 tour of the project.

Timeline

  1. 1905: Fresno Canal and Irrigation Company built the headgate.

  2. 1920: The Fresno Irrigation District bought the headgate.

  3. Oct. 27, 2026: Tour of the headgate project.

  4. Nov. 25, 2026: Headgate project expected to be completed.

Industry Context

Using a portable Portadam system instead of a temporary cobble dam reflects a shift toward less intrusive methods for canal infrastructure work. The approach also frees district staff for other tasks, including preparing for possible heavy winter storms.

Farms and households that rely on Fresno Canal irrigation water may see work-related interruptions while the headgate is being upgraded. The project's completion targeted for Nov. 25 determines when the upgraded gates return to normal operation.

The takeaway

Long-lived canal infrastructure like the 1905 headgate often needs staged upgrades that keep water moving during construction. Readers following local water projects can track district announcements for completion updates.

What happens next

The district plans to install individual motors for every gate so each can be controlled independently, and it aims to be ready to take flood releases during the El Niño year.

Further reading

For more on regional infrastructure projects, explore Construction coverage in Fresno.

Source note: This article includes information reported by SJV Water.

Live Poll

Do you trust your local water district to spend public money wisely?