The City of Fresno is spending $1.2 million to replace an aging First Street water main between Shields and Princeton avenues, causing lane closures and four-way stops. AI Illustration. Upload story photo >

The City of Fresno is replacing an aging underground water main on First Street between Shields and Princeton avenues. Lane closures and four-way stops are disrupting traffic at Shields and Princeton avenues while Walsh Montgomery Construction Inc. performs the work.

Why it matters

The original steel and cast-iron main, installed in the 1950s, has reached the end of its service life. A recent water main break caused a large sinkhole and flooded homes in southeastern Fresno, underscoring the need for replacements across the city.

The $1.2 million contract, awarded to Walsh Montgomery Construction in April and funded from the city's Water Enterprise Fund, covers one stretch of main in a system of about 1,900 miles. The city's fiscal 2027 budget sets $12.6 million for water main replacements, but the total cost of replacing the roughly 250 miles of aging pipe remains unstated.

The players

Walsh Montgomery Construction Inc.

The contractor performing the First Street water main replacement under its $1.2 million city contract.

The details

The project replaces the old pipe with ductile iron and polyvinyl chloride pipe and includes connection work on Simpson Avenue, water service transfers, trenching and pavement restoration. Walsh Montgomery expects to complete the work by late January.

Timeline

  1. April 2026: City awarded the $1.2 million water main contract to Walsh Montgomery Construction.

  2. Late January 2027: Walsh Montgomery expects to complete the First Street water main work.

  3. Spring 2027: City expects to begin repaving First Street between Shaw and Barstow avenues.

  4. Summer 2027: Repaving between Tulare and Olive avenues is expected to begin.

Industry Dynamics

The First Street project is one of the replacements targeting the roughly 250 miles of Fresno water mains that are past or within 10 years of the end of their useful life. It follows the same pattern as the city's fiscal 2027 water main replacement program, which is funded at $12.6 million.

Drivers on First Street between Shields and Princeton avenues face lane closures and four-way stops at Shields Avenue until the work finishes in late January. Residents served by the affected main may see water service transfers during construction.

The takeaway

Aging underground pipe is a citywide issue, with about 250 miles of Fresno's water mains near or past the end of their useful life. Residents driving or living near active construction zones should plan for detours and reduced lanes through the scheduled completion dates.

What happens next

Walsh Montgomery Construction expects to complete the First Street water main work by late January 2027. The city expects to begin repaving First Street between Shaw and Barstow avenues by spring 2027, with repaving between Tulare and Olive avenues expected to begin in summer 2027.

Further reading