Delegation Presses Feds on Flagstaff Flood Project

Arizona lawmakers and Flagstaff leaders urge faster federal action on the Rio de Flag Flood Control Project after deadly rainfall.

Updated on Nov. 22, 2026 in City Hall

Delegation Presses Feds on Flagstaff Flood Project

Live Poll

Do you trust your local government to finish flood protection projects on time?

Arizona's congressional delegation and Flagstaff city leadership pressed the federal government to prioritize the Rio de Flag Flood Control Project after extreme rainfall caused two deaths and extensive property damage in the city earlier in November. Flagstaff leaders met with U.S. Army Corps of Engineers officials in Washington D.C. to request that further delays be prevented.

Why it matters

The project is designed to protect approximately 1,500 structures in a flood plain on Flagstaff's Southside, and the letter described the improvements as an immediate public safety necessity. Its progress depends on federal funding alongside the city's share of the cost.

The project was first authorized in 2000 and has been re-authorized twice due to rising estimated costs, now evaluated at $244 million. The city pays 35% of that cost while federal Army Corps of Engineers funds cover the remainder, and it is unclear whether additional federal support will be committed.

The players

U.S. Army Corps of Engineers

The federal agency that designs the Rio de Flag project and pays for the majority of its cost, operating as the primary federal partner in flood control projects across the United States.

Mark Kelly

A Democratic U.S. senator from Arizona who cosigned the letter demanding that the Rio de Flag project be prioritized.

Reuben Gallego

A Democratic U.S. senator from Arizona who cosigned the letter demanding that the Rio de Flag project be prioritized.

The details

Sens. Mark Kelly and Reuben Gallego, along with Representatives Greg Stanton and Elijah Crane, signed a letter demanding that the Rio de Flag project be prioritized. The Corps designs the project and pays most of its cost, while the city has purchased land from the BNSF railroad and private property along the planned new channel.

Timeline

  1. 2000: Project first authorized under the Water Resources Development Act.

  2. Early November 2026: Extreme rainfall causes two deaths and property damage in Flagstaff.

  3. November 22, 2026: Delegation and city leadership press the federal government on project delays.

  4. March 2027: Planned deadline for awarding the construction contract.

  5. 2027: City aims to begin construction.

Seasonal Patterns

The project's 2000 authorization under the Water Resources Development Act has since been re-authorized twice as estimated costs rose, a pattern of cost growth that now runs roughly 25 years behind the flood risk it was designed to address.

Residents on Flagstaff's Southside live in a flood plain the project is meant to protect, so the pace of federal funding directly affects their flood risk. The city's 35% share of the $244 million cost means local budgets will also feel the outcome.

The takeaway

The Rio de Flag project shows how a flood control plan authorized more than two decades ago can still depend on federal funding decisions that determine whether nearby homes are protected in time.

What happens next

The city aims to award the construction contract by March 2027 and begin building the project next year.

Further reading

Follow local decisions on the project in the City Hall section for Flagstaff.

Source note: This article includes information reported by KJZZ.