SRP Delays Bartlett Dam Expansion to 2045

The Salt River Project's $4.4 billion plan to raise the dam 100 feet has been pushed back and will now be permitted in sequence rather than simultaneously.

Updated on Nov. 25, 2026 in Utilities

SRP Delays Bartlett Dam Expansion to 2045

Live Poll

Do you think local water supply is getting more secure in your area?

The Salt River Project has pushed back the Bartlett Dam expansion, now slated for completion in 2045 rather than the originally expected 2035. SRP informed stakeholders of the delay in August, as Arizona prepares to lose 760,000 acre-feet of Colorado River water annually starting next year.

Why it matters

The expansion is intended to add about 90,000 acre-feet of water per year to the Valley's supply at a time when Arizona faces a major cut to its Colorado River allotment. The delay and the shift to sequential permitting leave the region without that added capacity for nearly two more decades.

The expansion would raise the dam's height by 100 feet at an estimated cost of $4.4 billion, adding roughly 90,000 acre-feet per year, against Arizona's loss of 760,000 acre-feet of Colorado River water annually. The draft environmental impact statement and feasibility study remain pending, with a federal review still required.

The players

Salt River Project

A public power and water utility serving the Phoenix metropolitan area, which operates Bartlett Dam and is leading the expansion effort.

U.S. Bureau of Reclamation

The federal agency that manages Colorado River water infrastructure in the western United States and is now requiring sequential permitting for the dam project.

The details

Built in the late 1930s to form Bartlett Lake, the dam is operated by the Salt River Project, which had planned to complete the expansion by 2035. Reclamation now requires permitting to proceed sequentially rather than all at once, and SRP has released excess water downstream during heavy rains, including about 200,000 acre-feet earlier this month.

Timeline

  1. Late 1930s: Bartlett Dam is built to form Bartlett Lake.

  2. 2035: Original target completion date for the expansion.

  3. August 2026: SRP informs stakeholders that the project has been pushed back.

  4. Early 2028: SRP expects to submit a feasibility study to Congress.

  5. 2045: Revised expected completion date for the expansion.

Market Landscape

Arizona's loss of 760,000 acre-feet of Colorado River water annually, starting next year, makes the Bartlett Dam expansion a key piece of the state's effort to add local supply. The 2045 completion target means that added capacity will not arrive until well after the reduction takes effect.

Arizona water users will face a reduced Colorado River supply starting next year, and the Bartlett Dam expansion that could have added 90,000 acre-feet per year will not be available until 2045. Residents should expect continued reliance on current local supplies and conservation measures in the meantime.

The takeaway

The delay underscores how long major water infrastructure takes to permit and build, so planning for reduced river supplies must begin well before new capacity comes online. Arizona's water future will depend on decisions that extend far beyond the next few years.

Further reading

Explore more Arizona utilities coverage for context on regional water and power infrastructure.

Source note: This article includes information reported by Axios.