ALDOT Advances I-10 Mobile River Bridge Work
Foundation and approach work on the six-lane cable-stayed bridge is underway, with completion targeted for October 2031.
Updated on Nov. 29, 2026 in Industry

Live Poll
Do you think major bridge construction is worth the commute disruption in your area?
The Alabama Department of Transportation reported that foundation work for the Mobile River Bridge towers began in October 2026, and construction of the east approach bridge started in November 2026. The project links the new six-lane cable-stayed bridge to the existing Bayway on the eastern side of the Mobile River and to the I-10 corridor on the west.
Why it matters
The project will reshape how traffic crosses the Mobile River along the I-10 corridor, linking the existing Bayway and I-10 connections through a new bridge. Its progress will shape regional travel for Mobile residents over the coming years.
The project is a six-lane cable-stayed bridge with ALDOT anticipating completion in October 2031. Specific schedules for later construction milestones have not been published and will be announced as work advances.
The players
Alabama Department of Transportation (ALDOT)
The state agency responsible for planning, building, and maintaining Alabama's highways and bridges, and the source of the construction milestone update for this project.
The details
Crews have begun foundation work on the east and west towers over the Mobile River and started the east approach bridge that connects the new span to the existing Bayway. Future phases will include erecting the towers, building the main span superstructure, installing stay cables, and completing the main spans.
Timeline
October 2026: Foundation work began on the Mobile River Bridge towers.
November 2026: Construction began on the east approach bridge.
January 2027: Construction of the west approach bridge is scheduled to begin.
October 2031: ALDOT anticipates project completion.
Construction Timeline
This update advances the phased I-10 Mobile River Bridge and Bayway program, moving from tower foundations and east approach work toward the west approach and main span. The project remains on a multi-year schedule with completion targeted for October 2031.
Drivers crossing the Mobile River along I-10 and the Bayway should expect ongoing construction phases through 2031 as the new bridge is built. The project is designed to link the existing eastern and western connections through a six-lane cable-stayed span.
The takeaway
The new six-lane cable-stayed bridge is moving from foundations into approach and main span construction, with completion currently targeted for October 2031. Commuters who rely on the I-10 and Bayway corridor should plan for phased work over the coming years.
What happens next
Construction of the west approach bridge is scheduled to begin in January 2027, and more detailed schedules for later milestones will be announced as work progresses.
Further reading
Explore more Mobile construction coverage to follow other local projects shaping the city.
Source note: This article includes information reported by Fox10tv.
Live Poll
Do you think major bridge construction is worth the commute disruption in your area?