Alabama Starts Mobile River Bridge Foundation Work
Crews have begun work on the east and west towers of the $3.2 billion I-10 Mobile River Bridge project.
Updated on Nov. 26, 2026 in Industry

Live Poll
Do you think major bridge projects in your area are worth the cost?
The Alabama Department of Transportation began foundation work for the east and west towers of the I-10 Mobile River Bridge in October 2026. Construction on the east approach bridge followed in November 2026, as part of the Mobile River Bridge and Bayway Project.
Why it matters
The project replaces a key segment of the Interstate 10 corridor serving the Gulf Coast, and hazardous-material freight vehicles currently cannot use the Wallace Tunnel, so they must travel through local streets and surrounding communities. Phase One is expected to reshape traffic flow in Mobile for years to come.
The Phase One program carries a $3.2 billion total cost, financed in part by a $2.52 billion TIFIA loan from the U.S. Department of Transportation's Build America Bureau. The new six-lane cable-stayed crossing will be joined by reconstruction of approximately one mile of the existing Bayway and restriping of the 7.5-mile facility to three lanes in each direction.
The players
Alabama Department of Transportation
The state agency responsible for planning, building and maintaining Alabama's highway and bridge network, overseeing the I-10 Mobile River Bridge project.
Alabama Toll Road, Bridge and Tunnel Authority
The state authority that secured the financing for Phase One of the Mobile River Bridge and Bayway Project in September 2026.
Kiewit Massman Traylor
A joint venture of construction firms delivering the Phase One program through a design-build contract.
U.S. Department of Transportation
The federal department whose Build America Bureau provided a $2.52 billion TIFIA loan for the project.
The details
The Kiewit Massman Traylor joint venture is delivering the program through a design-build contract. The new six-lane cable-stayed crossing will carry the main span across the Mobile River, while the east approach bridge will connect it to the existing Bayway on the eastern side of the river.
Timeline
September 2026: The Alabama Toll Road, Bridge and Tunnel Authority secured financing for Phase One and construction was authorized.
October 2026: Foundation work began on the east and west towers of the Mobile River Bridge.
November 2026: Construction began on the east approach bridge.
January 2027: Construction of the west approach bridge is scheduled to begin.
October 2031: The Mobile River Bridge and Phase One improvements are anticipated to be completed.
Construction Landscape
The Mobile River Bridge and Bayway Project is being financed in part through a $2.52 billion TIFIA loan from the U.S. Department of Transportation's Build America Bureau, a federal credit tool used to leverage large highway investments. The project's design-build delivery by Kiewit Massman Traylor reflects a common approach for major Gulf Coast crossings that compresses schedules by overlapping design and construction.
Drivers on I-10 and the Bayway should expect lane shifts and restriping across the 7.5-mile facility as Phase One proceeds. Hazardous-material freight will continue to bypass the Wallace Tunnel and travel local streets until the new crossing is complete.
The takeaway
The Mobile River Bridge work is a multi-year commitment, with Phase One finishing in October 2031 and a Phase Two dependent on future funding. Commuters and freight operators should plan routes around construction phases as each stage opens.
What happens next
West approach bridge construction is scheduled to begin in January 2027, and Phase One completion is anticipated in October 2031.
Further reading
Explore more local projects in our Construction section for Mobile infrastructure coverage.
Source note: This article includes information reported by Constructionreview.