The City of Huntsville plans a January 2027 groundbreaking for the first housing units of the $400 million Mill Creek Choice Neighborhood Initiative, a multi-year project in partnership with the Huntsville Housing Authority. Financing for the development closed in early November 2026, and site work is underway.
Why it matters
The project aims to redevelop the Butler Terrace and Johnson Towers area with 725 housing units across income levels, including workforce housing for Huntsville Hospital employees. For Huntsville residents, it represents more than $350 million in public and private investment in the Mill Creek neighborhood.
The $400 million project is backed by a $50 million HUD Choice Neighborhoods Grant and calls for 725 units, including 84 in the first-phase Universal Design Building. Phase one is expected to take about 16 months of construction, and the stub does not specify how the remaining phases will be funded beyond the grant and closed financing.
The players
Huntsville Housing Authority
The Huntsville Housing Authority is the local public agency that partners with the city to oversee the Mill Creek redevelopment and affordable housing efforts.
U.S. Department of Housing and Urban Development
The U.S. Department of Housing and Urban Development is the federal agency that provides the $50 million Choice Neighborhoods Grant supporting the project.
Huntsville Hospital
Huntsville Hospital is a major regional medical center whose employees will be served by workforce housing included in the development.
The details
Phase one will include the 84-unit Universal Design Building at Governors Drive and 1st Street, with construction beginning early next year. Phase two will add 100 senior housing units, and the project is supported by an environmental assessment and ongoing site work.
Timeline
Early November 2026: financing for the development closed.
January 2027: targeted groundbreaking for the first housing units.
June 2028: phase one completion expected.
2032: total project completion targeted.
Program Context
The Mill Creek initiative applies the federal Choice Neighborhoods program, which pairs a HUD grant with local housing authority partnership to redevelop distressed public housing into mixed-income communities. Its $50 million grant places Huntsville's project within that national model rather than as a standalone local effort.
Residents of the Butler Terrace and Johnson Towers area will see the surrounding neighborhood redeveloped over the coming years, with mixed-income housing that includes units for low, medium and market-rate households. Construction on the Governors Drive site will bring active work to the area beginning early next year.
The takeaway
The Mill Creek project shows how a federal grant can anchor a mixed-income redevelopment that pairs new housing with workforce access for local employers. Residents tracking the project can watch for the January groundbreaking as the first visible sign of construction.
What happens next
Groundbreaking on the first housing units is targeted for January 2027, with phase one completion expected by June 2028.
Further reading
For more on how the city is shaping local housing and redevelopment, see City Hall.
Source note: This article includes information reported by Al.
Live Poll
Do you support building more mixed-income housing in your community?