Huntsville Builds $70M Pinhook Creek Corridor

The city's Pinhook Creek project includes flood mitigation, a linear park and a Memorial Parkway Skybridge slated for 2030.

Updated on Nov. 20, 2026 in Industry

Photograph of a creek channel under reconstruction beside a wide parkway, with stacked concrete blocks at the water's edge and a long pale pedestrian skybridge spanning overhead.
The city of Huntsville is building a $70 million Pinhook Creek corridor with flood mitigation, a linear park, and a 1,400-foot Memorial Parkway Skybridge slated for 2030. AI Illustration. Upload story photo >

Live Poll

Do you trust Huntsville to finish its downtown construction projects on schedule?

Huntsville is constructing the $70 million Pinhook Creek-Pedestrian Access and Redevelopment Corridor, which is currently underway with creek channeling along Memorial Parkway. The project includes a linear park and the Skybridge across Memorial Parkway, with completion targeted for 2030.

Why it matters

The city received more than $50 million in federal grant money for the project, which requires completion within five years. The work is expected to reshape the area around the Von Braun Center and Clinton Avenue for residents and visitors in Huntsville.

The $70 million project is supported by more than $50 million in federal grant money, which requires completion within five years. The source does not say how the balance of funding is being covered or whether the 2030 target will hold.

The players

City of Huntsville

Huntsville is the municipal government overseeing the Pinhook Creek project and its federal grant obligations.

The details

The first phase includes flood mitigation and restoration of Pinhook Creek, with channeling along the parkway currently underway. The contractor began on the east bank first and set blocks behind the Von Braun Center after a delay while blocks were manufactured. The Skybridge is 1,400 feet long and 12 feet wide, with construction expected to take three years.

Timeline

  1. Work on the project officially began last year.

  2. The new channel is expected to be visible by the middle of next year.

  3. The contractor is expected to demolish the existing railroad bridge by the middle of next year.

  4. Skybridge construction is expected to begin by late next year.

  5. Project completion is targeted for 2030.

Construction Timeline

The Pinhook Creek project is being built against a federal grant that requires completion within five years, placing its 2030 target inside that window. Its phased sequence of flood mitigation, creek restoration and Skybridge construction follows the grant's expectations for staged delivery.

Residents near Memorial Parkway, the Von Braun Center and Clinton Avenue should expect ongoing construction activity as creek channeling and the linear park take shape. The Skybridge across Memorial Parkway will add a pedestrian crossing once completed, though the source gives no closure or detour details.

The takeaway

Large public projects can stretch across several years and multiple phases, so the completion date is best read as a target. For Huntsville residents, the Pinhook Creek work is a multi-year effort tied to federal funding conditions.

What happens next

The new channel is expected to become visible by the middle of next year, when the contractor is also expected to demolish the existing railroad bridge. Skybridge construction is expected to begin by late next year.

Further reading

For more on local building work, see Construction coverage across Huntsville.

Source note: This article includes information reported by Al.