Applied Digital Signs 150MW Hyperscaler Lease

The 18-year lease with an unnamed investment-grade hyperscaler is backed by a $300 million bridge facility for Delta Forge 1 construction.

Updated on Nov. 24, 2026 in Data Centers

Bold flat-color editorial illustration of a row of dark server enclosures and cooling units on a concrete pad under open sky, with a rust-colored conduit in the foreground.
Applied Digital signed an 18-year lease for 150 megawatts of capacity with an unnamed investment-grade hyperscaler, carrying $5.4 billion in base-term revenue. AI Illustration. Upload story photo >

Live Poll

Do you think AI data center expansion is worth the cost to everyday electricity bills?

Applied Digital signed an 18-year lease for 150MW of capacity with an unnamed investment-grade hyperscaler, carrying base-term revenue of $5.4 billion. The company also received a $300 million senior secured bridge facility to fund construction of its Delta Forge 1 campus.

Why it matters

The lease adds to Applied Digital's contracted portfolio, which exceeds $41 billion in base-term revenue and more than 1.6GW of critical IT load. It reflects continued demand from large cloud and AI operators for dedicated data center capacity across the United States.

The 150MW lease is measured against a portfolio of more than 1.6GW of total contracted critical IT load and 2.2GW of grid-connected peak load. The tenant's identity and the specific power and cooling specifications for the Delta Forge 1 campus are not disclosed in the source.

The players

Applied Digital

Applied Digital was founded in 2021 as Applied Blockchain and develops data center campuses for high-density computing customers, with sites in Louisiana, North Dakota and Alabama.

The details

Applied Digital plans to fund the build first with equity already on its balance sheet, followed by a $5 billion programmatic equity partnership with Macquarie Asset Management and project financing supported by the long-term lease. The $300 million delayed draw term loan has a 364-day maturity and bears interest at SOFR plus 300 basis points.

Timeline

  1. November 24, 2026: Lease announcement published.

  2. First quarter of 2027: Applied Digital expects to complete remaining project finance for Delta Forge 1 and Polaris Forge 3.

  3. Second quarter of 2027: Applied Digital expects to complete project finance for Delta Forge 2.

  4. First half of 2028: Delivery of the leased capacity is expected.

Market Landscape

The lease fits a pattern in which developers secure multi-decade contracts with investment-grade hyperscalers before financing construction, a structure that lets them raise capital against contracted revenue. Applied Digital's portfolio of more than $41 billion in base-term contracted revenue places it among firms pursuing this model across the United States.

For most readers the lease does not change daily technology use directly, but it signals additional data center capacity coming online in Louisiana and other states over the next few years. Its effect on consumer cloud and AI service costs is not addressed in the source.

The takeaway

Large, long-term leases with investment-grade tenants are becoming a central tool for financing new data center capacity, and tracking how developers convert contracted revenue into built capacity shows whether announced projects reach their stated delivery dates.

What happens next

Applied Digital expects to complete project finance for Delta Forge 1 and Polaris Forge 3 in the first quarter of 2027, with Delta Forge 2 financing following in the second quarter of 2027. Delivery of the leased capacity is expected in the first half of 2028.

Further reading

For broader context on how the sector is expanding, see Data Centers coverage across the United States.

Source note: This article includes information reported by Datacenterdynamics.