CBO Puts Trump-Class Battleships at $275 Billion
The Congressional Budget Office estimates the Navy's 15-ship battleship plan would cost $275 billion, excluding research and development.
Updated on Nov. 23, 2026 in Military

Live Poll
Do you think the U.S. should spend more on its military?
The Congressional Budget Office estimates that the Navy's 15 Trump-class battleships would cost $275 billion in constant 2026 dollars, excluding research and development, averaging $18.3 billion per ship. The estimate, reviewed from the Navy's FY2027 shipbuilding plan, is higher than the Navy's earlier figures.
Why it matters
The CBO estimate exceeds the Navy's earlier projections of $15.1 billion for the lead ship and $9.7 billion on average for follow-on ships, in part because those earlier figures did not include nuclear propulsion. The Navy's plan replaces 28 DDG(X) destroyers with the battleships, and the CBO warns that final assembly at Newport News Shipbuilding in Virginia could delay carrier and submarine deliveries.
The CBO estimates the first Trump-class ship at $23.4 billion and the remaining 14 at about $18 billion each, against the Navy's earlier $15.1 billion and $9.7 billion figures. The estimate excludes research and development, and the CBO's warning about delays to carrier and submarine deliveries has not been quantified.
The players
Congressional Budget Office
The nonpartisan agency that provides cost and budget analysis to Congress, and whose review of the Navy's plan produced the $275 billion estimate.
Newport News Shipbuilding
A Virginia shipyard and the only U.S. yard certified to build nuclear-powered surface ships, where battleship final assembly is planned.
The details
The Navy named the lead ship USS Defiant in December 2025 and plans to buy the first battleship in FY2028, with further purchases in FY2030 and FY2031. The Navy requested $1 billion in advance procurement for FY2027 and proposes $7.2 billion over FY2027 to FY2031 to improve productivity at nuclear shipbuilders, while the plan also includes 57 Flight III Arleigh Burke-class destroyers at about $3.2 billion each.
Timeline
December 2025: Trump-class battleship announced, with USS Defiant named as lead ship.
August 2025: CBO first issued its battleship cost estimate, which has not changed since.
November 19, 2026: CBO published its review of the Navy's FY2027 shipbuilding plan.
FY2027: Navy requested $1 billion in advance procurement for the battleships.
FY2028: First battleship purchase is scheduled.
Defense Budget Context
The CBO's review of the FY2027 shipbuilding plan reveals that the battleship cost projections were revised upward after the Navy selected nuclear propulsion late in planning. The plan replaces 28 DDG(X) destroyers with 15 battleships, shifting the Navy's surface fleet priorities toward larger, nuclear-powered vessels.
The estimate signals that the battleship program's cost could exceed the Navy's earlier projections, which may affect future defense appropriations. Taxpayers will bear the cost of the program, and the CBO's warning about delays to carrier and submarine deliveries could affect the timing of those ships.
The takeaway
The gap between the Navy's earlier battleship estimates and the CBO's $275 billion figure underscores how late design decisions, such as adding nuclear propulsion, can substantially raise shipbuilding costs. Tracking whether final assembly at Newport News stays on schedule will show whether the program's timeline holds.
What happens next
The first battleship purchase is scheduled for FY2028, with further purchases in FY2030 and FY2031.