Generation Mining Finalizes Marathon Long-Lead Orders
Procurement commitments for the Ontario copper and palladium project exceed C$500 million, at or below prior estimates.
Updated on Nov. 25, 2026 in Industry

Generation Mining has finalized all long-lead item orders for its Marathon copper and palladium project in Ontario. Procurement commitments exceed C$500 million and are at or below costs estimated in the most recent feasibility study and construction budget.
Why it matters
The company replaced its original smaller mill and expansion pathway with a larger SAG mill, which provides 10.1 million tonnes a year of processing capacity from start-up and avoids C$12 million in future expansion costs. The change simplifies the plant design and removes the need for a pebble crusher.
Procurement commitments exceed C$500 million, and the larger SAG mill provides 10.1 million tonnes a year of capacity versus the 8.9 million originally planned. Detailed engineering by Ausenco is about 32% complete, leaving the remaining design work and final project cost not yet fully confirmed.
The players
Generation Mining
Generation Mining is a TSX-listed company focused on precious and base metals exploration and development.
Ausenco
Ausenco is an engineering and consultancy firm conducting detailed engineering on the Marathon project.
The details
The early works programme runs through the fourth quarter of 2026 and into 2027. The project is expected to be a long-life, low-cost operation producing 2.1 million ounces of palladium, 532 million pounds of copper, 488,000 ounces of platinum, 160,000 ounces of gold and three million ounces of silver over its 13-year mine life.
Timeline
Fourth quarter 2026: early works programme begins at the Marathon site.
2027: early works programme continues into the year.
Market Landscape
The decision to front-load capacity with a larger SAG mill departs from the staged smaller-mill approach set out in the project's original plan. It positions Marathon as a long-life copper and palladium operation in Ontario, where it must compete for capital and offtake against other base-metal developers.
For Ontario residents, the project signals sustained mining activity and potential employment tied to the Marathon site as early works proceed through 2027. Shareholders and investors will watch whether procurement and engineering stay at or below the feasibility-study budget.
The takeaway
Replacing a staged expansion with a larger mill up front can lower long-term costs for a mining project, but investors should track whether detailed engineering, now about 32% complete, holds the budget as work advances.