Waasigan Transmission Line Phase One to Energize
Hydro One's $1.2 billion 230-kV project in Northwestern Ontario is expected to be energized by the end of November 2026.
Updated on Nov. 18, 2026 in Business

Live Poll
Do you think Northwestern Ontario's electricity system is getting better or worse?
Hydro One's Waasigan Transmission Line phase one is set to be energized, with all 497 towers now in place for the 365-kilometre 230-kV line. Phase two, running from Atikokan to Dryden, is underway and scheduled for completion by late 2027.
Why it matters
Hydro One has said existing infrastructure in Northwestern Ontario is nearing capacity, and the project is designed to address that constraint. The entire $1.2 billion project is a 50/50 partnership between Hydro One and nine area First Nations.
The $1.2 billion project features 497 towers for phase one and 481 for phase two, with phase one spanning 365 kilometres of 230-kV line. A further 162-kilometre line between Dryden, Ear Falls and Red Lake is still in planning.
The players
Hydro One
Hydro One is Ontario's largest electricity transmission and distribution company, responsible for delivering power across much of the province.
The details
Construction of the 230-kV line began in late 2024 and was built in two phases, requiring nearly 500 new transmission towers for the first phase alone. The project is a 50/50 partnership between Hydro One and nine area First Nations.
Timeline
Late 2024: Construction of the 230-kV line began.
November 2024: A groundbreaking ceremony was held in Shuniah.
End of November 2026: An announcement that phase one is energized is expected.
Late 2027: The entire $1.2 billion project is scheduled for completion.
Market Landscape
The Waasigan project builds out high-voltage transmission capacity in Northwestern Ontario, a region where Hydro One has said existing infrastructure is nearing its limits. The phased, partnership-based approach with First Nations shapes how new regional grid capacity is financed and delivered.
Residents and businesses in Northwestern Ontario will see expanded transmission capacity as the line is energized and completed. Electricity demand in the Red Lake region could increase by 500 per cent over the next 25 years, which the new infrastructure is intended to support.
The takeaway
Expanded high-voltage capacity in Northwestern Ontario is being built now to meet demand that could rise sharply over the coming decades. Residents and local businesses should watch for the phase one energization announcement and the late 2027 completion date.
What happens next
An announcement that phase one of the Waasigan Transmission Line is energized is expected by the end of November 2026, and the full $1.2 billion project is scheduled for completion by late 2027.
Further reading
For broader context on how the province plans and funds power infrastructure, explore more Utilities coverage across Ontario.
Source note: This article includes information reported by TBNewsWatch.