Artemis Gold Reports 14% Q3 Output Rise
Blackwater mine produced 69,546 oz of gold in the third quarter of 2026, with the company on track for full-year guidance.
Updated on Nov. 20, 2026 in Business

Artemis Gold reported that its Blackwater mine in central British Columbia produced 69,546 oz of gold in Q3 2026, up 14% year-on-year. Year-to-date production reached 205,532 oz.
Why it matters
The results put the company on pace to meet its full-year guidance of 265,000 to 290,000 oz, which is central to its operating outlook. Expansion work underway at the site is intended to raise throughput and future output for British Columbia's gold sector.
Blackwater milled 1.48 million metric tons in Q3 2026 at an average grade of 1.55 g/mt gold, with 90% overall recovery. Contractor rectification work on leach circuit tanks is ongoing, and its effect on later quarters is not addressed.
The players
Artemis Gold
Artemis Gold is a Canadian gold mining company that operates the Blackwater project in central British Columbia.
The details
Production was supported by the process plant, while contractor work on leach circuit tanks continues. Phase 1A expansion, which adds a 3.5 MW vertical mill and extra leach tanks, is 77% complete and will lift design throughput by 33% to 8 million mt/y. Two storage ponds were added near the site for fresh and recycled process water.
Timeline
Q3 2026: Blackwater produced 69,546 oz of gold.
Q4 2026: Scheduled completion of the Phase 1A expansion.
December 2026: Planned Phase 1A commissioning.
2029: Expanded Phase 2 is projected to exceed 500,000 oz of annual gold production.
Market Landscape
Blackwater's Phase 1A expansion, which lifts design throughput by 33% to 8 million mt/y, is the step that the company's projected production above 500,000 oz in 2029 depends on. The quarterly output figures therefore indicate whether the company is moving along the staged Phase 1A and Phase 2 build-out it has laid out.
For British Columbia investors and mining-sector watchers, the output figures show whether Artemis Gold is meeting its stated production path. Completion of the Phase 1A expansion in Q4 2026 is the next milestone that would affect the company's capacity.
The takeaway
Artemis Gold's year-to-date output of 205,532 oz and its on-track guidance make the Phase 1A commissioning in December 2026 the key date to watch for the Blackwater mine's near-term production.
What happens next
Commissioning of the Phase 1A expansion is planned for December 2026, and completion is scheduled for Q4 2026.