Trans Mountain Raises Pipeline Capacity 10%
The first optimization step lifts the line to 980,000 barrels per day, with a second phase now under regulatory review.
Updated on Nov. 17, 2026 in Oil and Gas

Live Poll
Do you expect gasoline prices in your area to rise over the next year?
Trans Mountain completed the first step of its pipeline optimization in October, raising capacity 10 per cent to 980,000 barrels per day. The company filed an application in August for a second step that would add 210,000 barrels per day of capacity near Kamloops.
Why it matters
The pipeline reached capacity in June and began apportioning access, and S&P Global reported it was oversubscribed by seven per cent in October. Asian demand for Canadian oil grew after the U.S. war with Iran disrupted shipments through the Strait of Hormuz.
The first step added 90,000 barrels per day at a cost not stated in the source, while the second step, estimated at up to $4 billion, would add 210,000 barrels per day. The proposed Pacific Link pipeline, estimated at $44 billion, remains under business-case review with its final scope unresolved.
The players
Trans Mountain Corp.
Trans Mountain Corp. is the Canadian company that operates the Trans Mountain pipeline, which carries crude oil from Alberta to the Burnaby terminus in British Columbia.
S&P Global
S&P Global is a financial information and analytics company whose market reporting on energy flows includes assessments of pipeline utilization.
Canada Energy Regulator
The Canada Energy Regulator is the federal body that oversees interprovincial and international pipelines and approves major operational changes to them.
The details
The first step installed drag-reducing agent equipment at 16 pump stations, which injects a fluid that reduces internal friction in the pipeline lines. The second step would add pumping stations and a pipeline loop near Kamloops, with Trans Mountain aiming to have those facilities in place by the end of 2028.
Timeline
June 2026: The first optimization step began after regulator approval, and apportioning of pipeline access started.
August 2026: Trans Mountain filed its application for the second optimization step near Kamloops.
October 2026: The first step was commissioned, and S&P Global reported the pipeline oversubscribed by seven per cent.
End of 2028: Target completion date for the second-step facilities.
Market Landscape
Asian buyers of Western Canadian Select are paying a premium while U.S. buyers demand steep discounts for Canadian heavy crude, which reflects a market where Trans Mountain's expanded access matters more to Canada's export options. The pipeline's expansion positions Canadian producers to reach Asian markets as Strait of Hormuz disruptions reshape global crude flows.
Because the pipeline is oversubscribed and apportioning access, producers shipping through it may face allocation limits until the capacity expansions are complete. The second step's target completion by the end of 2028 means those constraints could persist for some time.
The takeaway
Watch the Canada Energy Regulator's review of the second optimization step, since its outcome will determine whether Trans Mountain's capacity gains continue beyond the first 10 per cent. Producers planning shipments should account for apportioning until then.