Trans Mountain Expansion Seen Adding $270B to GDP

Signal49 Research estimates the pipeline project's national economic contribution between 2018 and 2044 across construction and operations.

Updated on Nov. 19, 2026 in Economics

Photorealistic view of a cleared pipeline corridor cutting through dense forest toward a distant ridge under flat overcast light, with a steel pipeline section on rollers.
Signal49 Research estimates the Trans Mountain Expansion Project will add $270 billion in real GDP to Canada between 2018 and 2044, across construction and operations. AI Illustration. Upload story photo >

Signal49 Research published an analysis estimating the economic impacts of the Trans Mountain Expansion Project, which entered commercial service in May 2024. The study projects the project will contribute $270 billion in real GDP to the Canadian economy between 2018 and 2044.

Why it matters

The estimates compare Canada's economic trajectory against a scenario in which the project was never built, quantifying its effect on national output, employment and government revenues. The figures give policymakers and the public a measure of the project's economic footprint across Canada, British Columbia and Alberta.

Construction-phase impacts were $42.4 billion in national real GDP, with British Columbia accounting for $30.3 billion and Alberta $6.9 billion. Projected government revenues total $97.5 billion between fiscal years 2018-19 and 2044-45.

The players

Trans Mountain Expansion Project

A pipeline expansion project that increases the capacity of the Trans Mountain system carrying Alberta crude oil to the British Columbia coast for export.

Signal49 Research

A research firm that produces macroeconomic forecasting and economic impact assessments, and which published this analysis of the project.

The details

The analysis, published by Signal49 Research, models the project's construction phase from 2018 to 2025 and its operational phase from 2024 through 2044. Oil sands production gains in Alberta are estimated to drive an average annual increase of $9.6 billion in GDP and support 19,500 jobs per year.

Timeline

  1. 2018-2025: Construction phase of the Trans Mountain Expansion Project.

  2. May 2024: Project entered commercial service.

  3. 2024-2044: Operational phase of the project.

  4. 2018-19 to 2044-45: Period covered by the projected $97.5 billion in government revenues.

Economic Trajectory

The study frames the Trans Mountain Expansion Project against a counterfactual in which the pipeline was never built, extending the federal government's original rationale for the project with post-service economic estimates. Its projected $97.5 billion in government revenues is the fiscal component of that case.

Projected government revenues of $97.5 billion over fiscal years 2018-19 to 2044-45 indicate the project's fiscal effect on public finances. The estimates are modelled projections, so actual revenues and job figures may differ as operations continue.

The takeaway

Large infrastructure projects are often judged by modelled projections, so comparing estimates against actual results after commercial service begins will show how the economic case holds up. Readers tracking provincial output can watch Alberta and British Columbia figures as the operational phase proceeds.

Further reading

Explore more on Regional Economics to see how major infrastructure projects shape provincial output across Canada.

Source note: This article includes information reported by BOE Report.