Nine Datacentre Projects Await Victorian Approval

Nine datacentre proposals are waiting for government decisions days before the 28 November 2026 state election.

Updated on Nov. 24, 2026 in Data Centers

Nine Datacentre Projects Await Victorian Approval

Live Poll

Should new datacentres be allowed to be built near homes in your area?

Nine datacentre projects are currently awaiting approval according to the ministerial permits register, ahead of the Victorian state election on 28 November 2026. The planning minister released a statement of expectations covering applications submitted on or after 23 September.

Why it matters

The statement sets new rules that prohibit datacentres in residential, green wedge, rural and urban growth zones and within 150 metres of accommodation, education centres or hospitals. Community opposition, including a petition with more than 4,400 signatures against the GreenSquareDC proposal, has already caused delays.

The ministerial permits register lists nine datacentre projects awaiting decisions, with exceptions to the zoning prohibitions applying only within 5km of a 66,000-volt powerline or substation or where most electricity comes from renewable or battery storage. It remains unclear how many of the nine will meet those exceptions.

The players

NextDC

An Australian datacentre operator whose West Footscray M3 expansion has been delayed by community opposition.

GreenSquareDC

A developer behind the $1.5bn Spotswood datacentre proposal that has drawn a petition with more than 4,400 signatures.

DoverDC

A developer planning a $2.6bn, 200MW datacentre beside AusNet's South Morang terminal station.

Sonya Kilkenny

A Victorian public official serving as the state's planning minister, who released the statement of expectations for datacentre applications.

The details

The GreenSquareDC proposal, a $1.5bn, 240MW facility covering more than 105,000 square metres in Spotswood, was lodged with the planning minister at the end of July. Developers must display prominent signage onsite and publish detailed application documents online under the new expectations.

Timeline

  1. 31 July 2026: GreenSquareDC proposal lodged with the planning minister.

  2. 23 September 2026: Statement of expectations applies to applications submitted on or after this date.

  3. 28 November 2026: Victorian state election.

  4. February 2027: Earliest estimated restart of NextDC's approval process after the election, according to its chief executive.

Seasonal Patterns

The statement of expectations sets the zoning and distance rules that now govern the nine pending applications, with the 23 September cut-off separating projects subject to the new prohibitions from earlier submissions. Its restrictions against residential and green wedge zones and the 150-metre buffer around hospitals and schools define the planning framework for datacentres in Victoria.

Residents near proposed sites in Spotswood, South Morang and West Footscray could see changes to local land use and infrastructure depending on which projects are approved. Households may also feel the effects of large new power demands from facilities of 200MW to 240MW in their area.

The takeaway

Datacentre approvals in Victoria now hinge on the election result and on whether proposals clear the new zoning and distance rules. Readers in affected suburbs can track the ministerial permits register for updates on individual applications.

What happens next

The Victorian state election on 28 November 2026 will determine whether the approval process resumes, with NextDC estimating a restart no earlier than February 2027.

Further reading

Explore more on Data Centers for context on the state's pending approvals.

Source note: This article includes information reported by The Guardian.