EnergyAustralia Clarifies Tall Poles at Wooreen Battery
The tall poles going up at the Wooreen Energy Storage System are lightning rods, not lighting poles, the company says.
Updated on Nov. 23, 2026 in Energy

EnergyAustralia has clarified that tall poles being installed at the Wooreen Energy Storage System in Victoria's Latrobe Valley are lightning rods designed to protect battery equipment. The company also sold a 50 per cent share in the project to Banpu Energy Australia in July.
Why it matters
Neighbours had raised concerns that the poles signalled extra night-time brightness at the site, which sits next to EnergyAustralia's Jeeralang gas power plant. The clarification addresses the question directly as the battery nears its scheduled 2027 commissioning.
The Wooreen project is a 350 MW, 1,400 MWh battery with four hours of storage. Banpu paid about $110 million for a 50 per cent share, while the reported total project cost of $700,000 million has not been reconciled with those figures.
The players
EnergyAustralia
EnergyAustralia is an Australian energy company that continues to build and operate the Wooreen project and leads community engagement for it.
Banpu Energy Australia
Banpu Energy Australia is the Australian arm of the Thailand-based energy group Banpu, which acquired a 50 per cent share in the Wooreen project.
The details
The tall poles are lightning rods that attract strikes away from sensitive battery and inverter equipment, giving lightning a path into the site's earthing grid. Lights will be fitted at a lower height, close to the batteries and inverters, rather than on the tall poles.
Timeline
February 2025: EnergyAustralia broke ground on the Wooreen Energy Storage System.
July: EnergyAustralia sold a 50 per cent share in the project to Banpu Energy Australia.
Last week: EnergyAustralia posted a LinkedIn clarification about the lightning rods.
2027: The project is scheduled for completion and commissioning.
Roadmap
The Wooreen project extends the Latrobe Valley's shift from coal and gas generation toward grid-scale battery storage, built beside EnergyAustralia's existing Jeeralang gas plant. Its 1,400 MWh capacity places it among the larger storage projects in the region's transition.
Residents near the Wooreen site concerned about night-time lighting can expect lights on the poles to sit at a lower height, close to the batteries and inverters. The project's completion is scheduled for 2027.
The takeaway
Lightning protection and lighting are separate design choices at large battery sites, and clarifying which is which can prevent avoidable community concern about night-time brightness.