Marinus Link Sets Up Mardan Compound

Construction works for the Victoria–Tasmania transmission link begin at a temporary site near Mardan in November 2026.

Updated on Nov. 20, 2026 in Business

Wide view of white modular site cabins and parked earthmoving machinery on a gravel yard beside a flat rural paddock with a distant treeline.
Construction on the Marinus Link, the Victoria–Tasmania transmission project, is set to begin at a temporary Mardan compound in November 2026. AI Illustration. Upload story photo >

Live Poll

Do you support the Marinus Link cable project being built in your community?

Marinus Link will establish a temporary construction compound at Mardan, near the intersection of Mardan Road and Loves Lane, with establishment works expected during November and December 2026. The compound will provide site offices, parking and amenities for construction crews.

Why it matters

The Marinus Link is an undersea and underground electricity transmission link connecting Victoria and Tasmania, and the Mardan compound marks a step from planning into on-ground construction. Landholder access for surveys and pre-construction activities is being pursued through negotiated agreements, with compulsory acquisition sought where agreements cannot be reached.

Marinus Link has gained access to approximately 80 per cent of the land needed for design, surveys and construction planning, on a project costing a billion dollars. Remaining access depends on negotiated agreements and a pending application to the Victorian Government to compulsorily acquire easements.

The players

Marinus Link

Marinus Link is the undersea and underground electricity transmission project connecting Victoria and Tasmania, led by its developer team.

Prysmian

Prysmian is a major global cable manufacturer and installer that is preparing drilling works for the Sandy Point shore crossing.

TasVic Greenlink

TasVic Greenlink is the lead construction and civils contractor for the Marinus Link project.

The details

Establishment works at the Mardan compound are expected in November and December 2026, while Prysmian is preparing to mobilise in early 2027 for horizontal directional drilling at Sandy Point to create the underground shore crossing. TasVic Greenlink is Marinus Link's lead construction and civils contractor.

Timeline

  1. November and December 2026: Mardan compound establishment works expected.

  2. Early 2027: Prysmian mobilises for horizontal directional drilling at Sandy Point.

Market Landscape

The Marinus Link moves the Victoria–Tasmania interconnector from planning into physical construction, adding transmission capacity between the two states' electricity networks. Its progress through land access and contractor mobilisation will shape how quickly the link can carry power between them.

Landholders near the Mardan compound and Sandy Point may see construction activity and access negotiations in the coming months. Nearby residents should watch for updates from Marinus Link's community information centres in Leongatha and Burnie.

The takeaway

Large transmission projects move through land access, approvals and contractor mobilisation in stages, so early works like the Mardan compound signal the project's shift into construction. Residents affected by the route can follow updates through Marinus Link's community centres.

What happens next

Prysmian is expected to mobilise in early 2027 for horizontal directional drilling works at Sandy Point.

Further reading

Explore more on the Utilities sector and how Victoria's energy infrastructure is developing.

Source note: This article includes information reported by Sentinel-Times.