Inland Rail Sites Ready for Double-Stack Trains
All 12 Beveridge to Albury sites are now prepared for double-stacked freight, and the Tallarook passing loop has reopened after six months.
Updated on Nov. 20, 2026 in Business

Inland Rail has made all 12 sites along the Beveridge to Albury section ready for double-stacked freight trains. The Tallarook passing loop was commissioned and returned to service earlier this week after six months of closure.
Why it matters
Double-stacked capacity on the Beveridge to Albury corridor is a key step in the Inland Rail project's freight upgrade across Victoria. Reopening the Tallarook loop restores passing capacity on a section that had been out of service for half a year.
A 1.15-kilometre section of the Tallarook loop was lowered by 2.1 metres beneath the Hume Freeway, involving 4000 tonnes of material removed and 4000 tonnes of ballast installed alongside 1650 new sleepers. The extraction does not confirm the total cost of the works or when the remaining bridge and station projects will fully finish.
The players
Inland Rail
Inland Rail is a major Australian freight rail project designed to connect Melbourne and Brisbane through a faster, more efficient inland corridor.
John Holland
John Holland is one of Australia's largest construction and infrastructure companies, known for delivering major rail and transport projects.
The details
The Tallarook loop section was lowered by removing 4000 tonnes of material and replacing it with 4000 tonnes of ballast, with 1650 new sleepers installed. Track lowering and bridge replacements were also delivered at Barnawartha North, Glenrowan and Seymour Avenel Road under Tranche 1 of the Beveridge to Albury project.
Timeline
March 2023: B2A Tranche 1 project commenced.
June 2024: Work on B2A Tranche 2 began.
Earlier this week: Tallarook passing loop commissioned and returned to service.
End of 2026: Major bridge replacements and station upgrades at Wandong, Tallarook, Seymour, Broadford, Euroa and Benalla scheduled for completion.
Transportation Outlook
Double-stack readiness across all 12 Beveridge to Albury sites extends the staged delivery of the Inland Rail B2A program, which began its Tranche 1 works in March 2023. Tranche 2 followed in June 2024, and the Tallarook loop reopening marks a practical milestone in that sequence for Victorian freight corridors.
Residents and businesses near the Tallarook, Seymour, Broadford, Euroa and Benalla corridor will see continued bridge and station works through to the end of 2026. Freight traffic through Victoria is expected to benefit once double-stacked services begin, though the extraction does not give a start date.
The takeaway
Completing the Beveridge to Albury works in stages lets Inland Rail bring sections into service as they finish rather than waiting for the whole corridor. Readers tracking Victorian freight should watch the end-of-2026 completion dates for the remaining bridge and station projects.
What happens next
Major bridge replacements and station upgrades at Wandong, Tallarook, Seymour, Broadford, Euroa and Benalla are scheduled to be completed before the end of 2026, with final bridge works at Broadford and Wandong currently underway.
Further reading
For more on the state's freight network, see Transportation coverage across Victoria.
Source note: This article includes information reported by Rail Express.